Bayz

Check More Updates
Timelapes Video
2018-04-15
  • Guide wall work has been completed.
  • Soil excavation work has started and completed until 1.8 m depth.
  • Shoring & Piling work has started and completed 93 No’s of soft piles.
  • Shoring & piling work has started and completed 79 No’s of hard piles.
  • Capping beam preparation started.
2018-04-01
  • Enabling work contractor has been mobilized at site.
  • Soil excavation work has started and completed until 1.8 m depth.
  • Guide wall work has been completed.
  • Shoring &Piling work has started and completed 93 No’s of soft piles.
  • Preparation of Tender documents is in progress.
  • MEP detail design drawings is in progress.