Bayz

Check More Updates
Timelapes Video
2018-06-01
  • Guide wall work has been completed.
  • Soil excavation work has started and completed until 1.8 m depth.
  • Shoring & Piling work has started and completed 194 No’s of soft piles.
  • Shoring & piling work has started and completed 194No’s of hard piles.
  • Capping beam preparation started and 224 Rmt casted.
  • Concrete panel for shoring completed.
2018-05-15
  • Guide wall work has been completed.
  • Soil excavation work has started and completed until 1.8 m depth.
  • Shoring & Piling work has started and completed 172 No’s of soft piles. 
  • Shoring & piling work has started and completed 151No’s of hard piles.
  • Capping beam preparation started and 129 Rmt casted.
  • Concrete panel for shoring completed.