Bayz

Check More Updates
Timelapse Video
2019-01-01
  • Guide wall work has been completed.
  • Soil excavation work has started and completed till platform level.
  • Shoring & Piling work has started and completed 194 No’s of soft piles.
  • Shoring & piling work has started and completed 194No’s of hard piles.
  • Capping beam completed.
  • Concrete panel for shoring completed.
  • DM Building permit obtained.
  • Main contractor commenced works.
  • LIFT PIT blinding concrete casted.
  • LIFT pit sacrificial block work in progress.
  • Compaction for pile cap, works in progress.
  • Site mobilization in progress.
2018-12-15

Guide wall work has been completed.

  • Soil excavation work has started and completed till platform level.
  • Shoring & Piling work has started and completed 194 No’s of soft piles.
  • Shoring & piling work has started and completed 194No’s of hard piles.
  • Capping beam completed.
  • Concrete panel for shoring completed.
  • DM approvals obtained.
  • Main contractor mobilization started.