Bayz

Check More Updates
Timelapse Video
2018-11-01
  • Guide wall work has been completed.
  • Soil excavation work has started and completed till platform level.
  • Shoring & Piling work has started and completed 194 No’s of soft piles.
  • Shoring & piling work has started and completed 194No’s of hard piles.
  • Capping beam
  • Concrete panel for shoring completed.
  • DM approvals obtained.
  • Piling works completed and excavation in progress.
2018-10-15
  • Guide wall work has been completed.
  • Soil excavation work has started and completed till platform level.
  • Shoring & Piling work has started and completed 194 No’s of soft piles.
  • Shoring & piling work has started and completed 194No’s of hard piles.
  • Capping beam completed.
  • Concrete panel for shoring completed.
  • DM approvals obtained.
  • Piling works completed and excavation in progress.