JavaScript is off. Please enable to view full site.

Glamz

Check More Updates
Timelapes Video
2018-04-15
  • · Tower-1: Upper Roof floor Slab is in progress and roof parapet reinforcement and shuttering in progress
  • · Tower-1: Block Work at 14th floor is in progress.
  • · Tower-1: Block Work at 13th floor above lintel is in progress.
  • · Tower-1: Block Work at 12th floor above lintel is in progress.
  • · Tower-1: Plastering work at 5th and 9th floor is in progress.(6th,8th not yet started)
  • · Tower-1: Wall Tiling work on 4th and 7th floor is in progress.(5th,6th not yet started)
  • · Tower-1: Suspension for false ceiling 1st floor in progress
  • · Tower-1: wall primer and stucco 1st,2nd, 3rd in progress
  • · Tower-1: wet area water proof 1st floor started
  • · Tower-2: Slab Reinforcement and shuttering work for Upper Roof floor slab is in progress
  • · Tower-2: Block Work layout at 14th floor is in progress.
  • · Tower-2: Block Works at 13th, 12th floor up to Lintel Level is in progress.
  • · Tower-2: Block Works at 11th floor above Lintel Level is in progress.
  • · Tower-2: Plastering work at 7th and 8th floor is in progress.
  • · Tower-2: Wall Tiling work is progress on 3rd,4th and 6th in progress(5th not yet started)
  • · Tower-2: Suspension for false ceiling 1st floor in progress
  • · Tower-2: wall primer and stucco 1st to 4th in progress

 

MEP STATUS – GLAMZ (TOWER –A)

ELECTRICAL:

  • Wall conduit & DB Fixing- completed up to 10th floor, 11TH in progress.
  • POWER WIRING- 1st floor completed, 2nd in progress.
  • Emergency & Exit & Fire alarm wiring – up to 6th floor.
  • Lights wiring - 1st floor completed, 2nd in progress.
  • Structural cabling- not yet.

 

PLUMBING:

  • DRAINAGE – 7th floor in progress.
  • DRAINAGE RISER – up to 10th floor.
  • WATER SUPPLY PPR – 4th floor In progress
  • WATER SUPPLY PEX & WALL DRAIN – completed up to 10th floor, 11th in progress.

 

FIRE FIGHTING:

  • MAINLINE – 6th floor in progress
  • BRANCHES – 5th in progress.
  • RISER – done up to 3rd floor.

 

HVAC:

  • FCU- 1ST TO 9TH floor.
  • DUCTING – 1st in progress.

 

CHILLER PIPING:

  • MAINLINE –5th floor in progress.
  • BRANCHES –2nd floor in progress.

 

STARZ SUBSTATION IS APPROVED.

 

MEP STATUS– GLAMZ (TOWER –B)

ELECTRICAL:

  • Wall conduit & DB Fixing- 10th in progress.
  • Emergency & Exit & Fire alarm wiring – up to 5th floor
  • Lights wiring –2nd in progress.
  • POWER WIRING- 2nd in progress.
  • Structural cabling- Not yet.

 

PLUMBING:

  • DRAINAGE high-level – up to 7th floor.
  • DRAINAGE RISER – up to 10th floor .
  • WATER SUPPLY PPR – 2nd in progress.
  • WATER SUPPLY PEX & WALL DRAIN – 10th in progress.

 

FIRE FIGHTING:

  • MAINLINE –up to 4th floor.
  • BRANCHES – up to 4th floor.
  • RISER up to 4th floor.

 

HVAC:

  • FCU- 1ST TO 8TH floor
  • DUCTING – 1st in progress.

 

CHILLER PIPING:

  • MAINLINE – up to 4th floor
  • BRANCHES- up to 4th floor.

 

GLAMZ SUBSTATION IS APPROVED.

2018-04-01
  • Tower-1: slab shuttering work for Roof floor Slab is completed.
  • Tower-1: Block Work at 12th floor is in progress.
  • Tower-1: Plastering work at 7th and 9th floor is in progress.
  • Tower-1: Wall Tiling work on 2nd and 3rd floor is in progress.
  • Tower-2: Slab shuttering work for Roof floor slab is completed.
  • Tower-2: Block Work layout at 12th floor is in progress.
  • Tower-2: Block Works at 11th floor up to Lintel Level is in progress.
  • Tower-2: Plastering work at 1st to 5th floor is in progress.
  • Tower-2: Wall Tiling work is progressing well on 1stand 2nd floor.
  • Spray plastering works on Ceiling & Columns @ Podium-1&2 in progress.
  • Preparation for Epoxy Flooring @ Podium-1 & Podium-2 is in progress.

WALKTHROUGH VIDEO

PROJECT LOCATION