Miraclz

Check More Updates
Timelapse Video
2019-01-01

 Substructure:  

  • substructure works compelted- 100%

Floor Slab:  

  • Podium 1 floor slab casting completed – 100%
  • Podium 2 floor slab casting completion – 100%
  • roof of podium slab casting completion – 50% 
  • 2nd floor slab casting completion – 100%
  • 3rdfloor slab casting completion – 100%
  • 3rdto 4th floor columns Reinforcement completion -  20%

 

Core Wall: 

  • Core wall casting completed F5-F6 level – 100%
  • Core wall reinforcement completed F6-F7 level – 80%
  • Core wall shuttering completed F6-F7 level – 40%
2018-12-15

Substructure:

 

  • Raft casting completed
  • Dewatering stopped.
  • Waterproofing works for retaining wall is 100% completed.
  • Ground floor slab – 100%
  • Ramp from Basement to P2 floor casting completed.

Super Structure: 

 

  • Podium 1 floor slab casting completed – 100%
  • Podium 2 floor slab casting completion – 100%
  • Podium 2 roof floor slab casting completion – 50% 
  • 2nd floor slab completion – 100%
  • 3rd floor slab in progress- 25%

Core Wall: 

 

  • Core wall casting completed F4-F5 level – 100%
  • Core wall reinforcement completed F5-F6 level –50%
  • Core wall shuttering completed F5-F6 level – 30%