2018-06-01
  • Raft casting completed
  • Dewatering stopped.
  • Shoring block work 100% completed and guniting completed.
  • Waterproofing works for retaining wall is 100% completed
  • retaining wall concrete casting 100% completed
  • GF- First floor 100 % vertical casted.
  • Reinforcement for Ramp from Basement to ground floor in progress.
  • Core wall concrete casting 100% completed from Basement to Ground floor
  • Ground floor formwork 75% completed
  • Reinforcement for ground floor slab in progress
2018-05-15
  • Main Construction Contract awarded to M/s Naresco and mobilization completed.
  • Dewatering stopped.
  • Shoring block work 100% completed and guniting completed.
  • Waterproofing works for retaining wall is 65% completed
  • retaining wall concrete casting 45% completed
  • Main RAFT casted
  • GF- First floor 85 % vertical casted.
  • 2nd tower crane Erected.
  • Ramp shuttering from Basement to ground floor in progress.
  • Core wall reinforcement 100% completed
  • Core wall form work assembly in progress
  • Ground floor formwork 25% completed