Miraclz

Check More Updates
Timelapes Video
2018-04-15
  • · Submission for TIS approval done in RTA and approved.
  • · Main Construction Contract awarded to M/s Naresco and mobilization completed.
  • · Dewatering in progress.
  • · Shoring block work 100% completed and guniting completed.
  • · Waterproofing works 90% completed.
  • · Reinforcement and Lift pit concrete done and reinforcement raft areas in progress.
  • · Water tank, LIFT pit and Sump pit Raft casted.
  • · Main RAFT approved by DM and casting of raft in progress.
2018-04-01
  • Submission for TIS approval done in RTA and approved.
  • Main Construction Contract awarded to M/s Naresco and mobilization completed.
  • Dewatering in progress.
  • PCC 100% completed.
  • Shoring block work 100% completed and guniting completed.
  • Waterproofing works 90% completed.
  • Reinforcement and Lift pit concrete done and reinforcement raft areas in progress.
  • Water tank, LIFT pit and Sump pit Raft casted.