2018-11-01

 Substructure:

  • Raft casting completed
  • Dewatering stopped.
  • Waterproofing works for retaining wall is 100% completed
  • ground floor slab – 100%
  • Ramp from Basement to ground floor casting completed.

Floor Slab:

  • Podium 1 floor slab casting completion – 100%
  • Podium 2 floor slab casting completion – 45%
  • 1st floor floor slab works in progress– 35%

 

Core Wall:

 

  • Core wall castingcompleted F1-F2 level – 100%
  • Core wall reinforcement completed F2-F3 level – 80%
  • Core wall shuttering completed F2-F3 level – 40%
2018-10-15
  • Raft casting Completed
  • Ramp from Basement to ground floor casting completed.
  • Core wall casting completed P2 level – 100%
  • Core wall reinforcement completed F1 level – 15%
  • Core wall shuttering completed F1 level – 15%
  • Podium 1 floor slab casting completion as on date – 100%
  • Podium 2 floor slab shuttering completion as on date – 30%
  • Podium 2 floor slab casting completion as on date – 15%