Resortz

Check More Updates
Timelapes Video
2018-09-15

Structure:

  • Block no 3:

o   Roof floor slab (slab above level 4) formwork completed-100%

o   Roof floor (slab above level 4) reinforcement completed – 99%

o   Roof floor slab (slab above level 4) casting completed – 50%

 

  • Block no 2:

o   Roof slab (slab above level 4) formwork completed – 100%

o   Roof slab (slab above level 4) reinforcement works in progress – 65%

 

 

  • Block no 1:

o   Roof slab (slab above level 4) formwork in progress – 95%

o   Roof slab (slab above level 4) reinforcement in progress – 65%

o   Roof slab (slab above level 4) casting completed – 50%

 

Finishing works

  • Block 3:

o   Block work- Basement – 85 % completed.

o   Ceiling painting - Basement – 75 % completed.

o   Block work- ground floor-95% completed.

o   Plastering - ground floor- 15% completed.

o   Block work- first floor- 90% completed.

o   Plastering – First floor – 5% completed.

 

  • Block 2:

o   Block work - Basement – 80 % completed.

o   Ceiling painting - Basement – 20 % complete.

o   Block work- ground floor-90% completed.

o   Block work- first floor- 45% completed.

 

  • Block 1:

o   Block work - Basement – 80 % completed

o   Ceiling painting - Basement – 80 % completed

o   Block work- ground floor-85% completed

o   Block work- first floor- 80% completed

 

2018-09-01

Structure:

 

  • Water proofing works 98% completed.
  • Swimming pool slab casting done.
  • Ground floor slab 100% casting done.
  • Basement to ground floor Ramp casting completed.
  • Block no 3:

o   Raft completed.

o   Retaining wall completed.

o   Fourth floor slab casting – 100% completed

o   Columns /Shear walls for fourth floor to Roof casting - 50% completed.

o   Roof floor form work completed-65%

o   Roof floor slab reinforcement work completed-55%

 

  • Block no 2:

o   Raft completed.

o   Waterproofing for retaining walls completed.

o   Vertical element reinforcement from third floor to fourth floor in progress- 100% completed.

o   Fourth floor slab casting completed – 100%

o   Fourth to Roof columns completed – 90%

o   Roof Floor formwork in progress – 30%

 

  • Block no 1:

o   Raft completed

o   Waterproofing for retaining wall complete

o   Fourth floor slab casting completed – 100%

o   Fourth to Roof columns completed – 75%

o   Roof Floor formwork in progress – 55%

o   Roof Floor slab reinforcement in progress – 25%

 

Finishing works:

 

  • Block 3:

o   Block work- Basement – 80 % completed

o   Ceiling painting - Basement – 60 % completed

o   Block work- ground floor-90% completed

o   Block work- first floor- 90% completed

o   Plastering - ground floor- 5% completed

 

 

  • Block 2:

o   Block work - Basement – 80 % completed

o   Ceiling painting - Basement – 20 % complete

o   Block work- ground floor-85% completed

o   Block work- first floor- 40% completed

 

  • Block 1:

o   Block work - Basement – 80 % completed

o   Ceiling painting - Basement – 60 % completed

o   Block work- ground floor-80% completed

o   Block work- first floor- 65% completed

 

 

WALKTHROUGH VIDEO

PROJECT LOCATION