2018-04-15
  • · Construction NOC for foundation works received.
  • · Obtained NOC for office setup and mobilization of site office completed.
  • · Block work for shoring 100% completed.
  • · Water proofing works 95% completed.

 

Block no 3:

  • Raft completed.
  • Retaining wall completed.
  • Columns /Shear walls for Basement to Ground floor casting completed.
  • Ground floor slab casting completed.
  • Basement to ground floor Ramp casting completed.
  • GF to First floor verticals casted.
  • First floor slab decking 90% completed and Post tension works in progress.

 

  Block no 2:

  • Raft completed.
  • Waterproofing for retaining walls completed.
  • Vertical elements  Basement to GF completed
  • Ground floor Slab casting 80% completed.
  • GF to first floor columns casted.
  • Slab decking for First floor slab in progress.

 

  Block no 1:

  • Raft completed
  • Waterproofing for retaining wall complete
  • Basement to GF verticals completed.
  • GF slab 70% casting completed/
  • GF to first floor verticals in progress.
2018-04-01
  • Construction NOC for foundation works received.
  • Obtained NOC for office setup and mobilization of site office completed.
  • PCC 100% work completed.
  • Block work for shoring 100% completed.
  • Water proofing works 95% completed

 

Block no 3:

o   Raft completed.

o   Retaining wall completed.

o   Columns /Shear walls for Basement to Ground floor casting completed.

o   Ground floor slab casting completed.

o   Basement to ground floor Ramp casting completed.

o   GF to First floor verticals casted.

o   First floor slab decking 50% completed.

 

Block no 2:

o   Raft completed.

o   Waterproofing for retaining walls completed.

o   Tower crane erection completed.

o   Vertical elements  Basement to GF completed

o   Ground floor Slab casting 50% completed.

 

Block no 1:

o   Raft completed

o   Waterproofing for retaining wall completed.

o   Tower crane erection completed.

o   Basement to GF verticals completed.

o   GF slab decking in progress.