Resortz

Check More Updates
Timelapes Video
2018-06-01
  • Water proofing works 98% completed.
  • Swimming pool slab casting done
  • Ground floor slab 100% casting done

 

  • Block no 3:

o   Raft completed.

o   Retaining wall completed.

o   Columns /Shear walls for Basement to Ground floor casting completed.

o   Ground floor slab casting completed.

o   Basement to ground floor Ramp casting completed.

o   First floor slab casting completed- 100%

o   concrete for columns from 1st to 2nd casting done.

o   Reinforcement for core wall from level 1 to 2 completed and formwork in progress

o   First floor attic slab casting completed

o   Second floor formwork in progress- 50%

o   Second floor reinforcement for beam in progress

 

  • Block no 2:

o   Raft completed.

o   Waterproofing for retaining walls completed.

o   Vertical elements  Basement to GF completed

o   Ground floor Slab casting 100% completed.

o   First floor slab 100% completed for casting of concrete

 

  • Block no 1:

o   Raft completed

o   Waterproofing for retaining wall complete

o   Basement to GF verticals casting completed.

o   GF slab casting completed

o   First floor slab 99% shuttering completed.

o   First floor slab reinforcement in progress – 70%

o   GF to first floor verticals  casting completed

2018-05-15
  • Temporary shoring removal in progress.
  • Water proofing works 98% completed.
  • Swimming pool slab casting done
  • Ground floor slab 80% casting done

 

  • Block no 3:

o   Raft completed.

o   Retaining wall completed.

o   Columns /Shear walls for Basement to Ground floor casting completed.

o   Ground floor slab casting completed.

o   Basement to ground floor Ramp casting completed.

o   GF to First floor verticals casted.

o   First floor slab decking 100% completed.

o   Post tension and reinforcement works 100% completed.

o   50% slab casted for First floor

o   Reinforcement for verticals from 1st to 2nd in progress

o   First floor attic slab casting completed

 

  • Block no 2:

o   Raft completed.

o   Waterproofing for retaining walls completed.

o   Vertical elements  Basement to GF completed

o   Ground floor Slab casting 100% completed.

o   GF to first floor columns casting completed

o   GF to First Floor core wall casting completed

o   Slab decking 100% completed for First floor slab.

o   Reinforcement and post tension works for first floor slab in progress and 40% completed.

 

  • Block no 1:

o   Raft completed

o   Waterproofing for retaining wall complete

o   Basement to GF verticals casting completed.

o   GF slab 78% casting completed

o   GF slab 99% shuttering completed.

o   GF slab 100% reinforcement completed

o   GF to first floor verticals  casting completed

o   First floor slab formwork 35% completed.