Resortz

Check More Updates
Timelapse Video
2019-01-01

Structure: 

  • Substructure works completed- 100%.
  • Swimming pool slab casting for Rcc works completed.

 

Super Structure: 

  • Super structure 99% completed for block 1,2 and 3.

 

Finishing Works: 

  • Block work:

o   Ground floor- 95%

o   First floor- 95%

o   Second floor- 95%

o   Third floor- 95%

o   Fourth floor-85%

 

  • Plaster:

o   Ground floor-95%

o   First floor- 90 %

o   Second floor- 62%

o   Third floor- 10%

o   Roof- 70% 

 

  • Tiling:

o   Ground floor- 65%

o   First floor- 40%

o   Second floor - 15%

o   Third floor - 6%

 

  • Paint:

o   Basement - 90% 

 

MEP works: 

  • Basement       –   over all work completion – 75%
  • Ground floor   –   over all work completion - 80%
  • First floor        – overall work completion - 80%
  • Second floor   – overall work completion - 52%
  • Third floor   – overall work completion - 20%
2018-12-15

Super Structure:

 

  • Super Structure 100% completed for block 1,2 and 3 

Finishing Works:

 

Block work

  • Ground floor- 95%
  • First floor- 95%
  • Second floor- 95%
  • Third floor- 80%
  • Fourth floor-65%

Plaster

  • Ground floor-95%
  • First floor- 85%
  • Second floor- 40%
  • Roof- 55%

Tiling

 

  • Ground floor- 45%
  • First floor- 35%
  • Second floor - 15%
  • Third floor - 6%

Paint

 

  • Basement - 90% 

MEP Works:

 

  • Basement           – over all work completion – 75%
  • Ground floor      – over all work completion -80%
  • First floor             – overall work completion- 75%
  • Second floor       – overall work completion- 30%