Resortz

Check More Updates
Timelapse Video
2018-11-01

CIVIL Works:

 

Structure:

 

  • Substructure water proofing works 98% completed.
  • Swimming pool slab casting done.
  • Ground floor slab 100% casting done.
  • Basement to ground floor Ramp casting completed.

 

Super structure:

 

  • Super structure 99% completed for block 1,2 and 3.

Finishing works:

  • Block work

o   Ground floor- 95%

o   First floor- 85%

o   Second floor- 75%

o   Third floor- 60%

o   Fourth floor- 5%

  • Plaster

o   Ground floor-95%

o   First floor- 30%

o   Second floor- 5%

  • Tiling

o   Ground floor- 5%

o   First floor- 5%

  • Paint

o   Basement - 90%

 

MEP Works:

 

  • Basement       –   over all work completion – 63%
  • Ground floor –   over all work completion -61%
  • First floor        – overall work completion- 47%
2018-10-15

Structure:

  • Substructure water proofing works 98% completed.
  • Swimming pool slab casting done.
  • Ground floor slab 100% casting done.
  • Basement to ground floor Ramp casting completed.
  • Block No: 03

o   Raft completed.

o   Retaining wall completed.

o   super structure concrete slab casting – 100% completed

o   Roof to Top roof core walls casting completed – 100%

o   Top Roof slab shuttering completed – 95%

o   Top Roof slab reinforcement works completed – 95%

  • Block No: 02

o   Raft completed.

o   Retaining wall completed.

o   super structure concrete slab casting – 100% completed

o   Roof to Top roof core walls casting completed – 100%

o   Top Roof slab shuttering completed – 15%

  • Block No: 01

o   Raft completed.

o   Retaining wall completed.

o   super structure concrete slab casting – 100% completed

o   Roof to Top roof core walls reinforcement completed – 95%

o   Roof to Top roof core walls shuttering completed – 40%

 

  • Finishing works
  • Block 3:

o   Block work- Basement – 90 % completed

o   Ceiling painting - Basement – 85 % completed

o   Block work- Ground floor-95% completed

o   Plastering - Ground floor- 85% completed

o   Block work- First floor- 90% completed

o   Plastering – First floor – 15% completed

o   Block work- Second floor- 80% completed

o   Block work- Third floor- 35% completed

 

  • Block 2:

o   Block work - Basement – 80 % completed

o   Ceiling painting - Basement – 65 % complete

o   Block work- ground floor-90% completed

o   Plastering - Ground floor- 85% completed

o   Block work- First floor- 90% completed

o   Plastering – First floor – 2% completed

o   Block work- Second floor- 45% completed

o   Block work- Third floor- 20% completed

 

  • Block 1:

o   Block work - Basement – 80 % completed

o   Ceiling painting - Basement – 85 % completed

o   Block work- Ground floor - 90% completed

o   Plastering - Ground floor - 85% completed

o   Block work- First floor - 90% completed

o   Plastering – First floor – 2% completed

o   Block work- Second floor - 50% completed

o   Block work- Third floor- 20% completed

 

  • MEP works:

o   Over all Progress:

o   Basement – High level Plumbing works – Completed 80% 

o   High level HVAC works - Completed 70% 

o   High level FF works - Completed 65%  

o   Ground floor – High level Plumbing and drainage works – Completed 50%  

o   High level HVAC works - Completed 10%  

o   High level FF works - Completed 15%  

o   First floor – High level Plumbing works – In progress  

o   High level HVAC works – In progress  

o   High level FF works – In progress  