JavaScript is off. Please enable to view full site.

Glamz

Check More Updates
Timelapes Video
2018-09-15

CIVIL:

  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has been completed.
  • Tower-1: Block Work has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tiling work has been completed for all floors.
  • Tower-1: Suspension for false ceiling from 1st to 6th floor has completed.
  • Tower-1: False ceiling closing work from 1st to 6th floor has completed.
  • Tower-1: Wall primer and stucco 1st to 15th floor is in progress.
  • Tower-1: Wet area floor tiling work has been completed for all floors.
  • Tower-1: Dry area floor tiling work has been completed for all floors.
  • Tower-1: Corridor area floor tiling 2nd to 13th floor has completed
  • Tower-1: External plaster work on Elevation A, B, C, D is in progress
  • Tower-1: Sliding door installation is in progress on 2nd floor.
  • Tower-1: Wardrobe installation is in progress on 2nd to 6th floor.
  • Tower-1: Kitchen cabinet installation is in progress on 2nd to 6th floor.
  • Tower-1: wooden door installation is in progress on 2nd and 3rd floor.
  • Tower-1: Balcony installation is in progress on 2nd to 12th floor
  • Tower-1: Curtain wall installation is in progress on 1st to 15th floor Elevation A,B,C,D
  • Tower-2: Roof floor waterproofing has been completed.
  • Tower-2: Block Works has been completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tiling work has been completed for all floors.
  • Tower-2: Suspension work for false ceiling 1st to 5th floor has completed.
  • Tower-2: Wall primer and stucco 1stto 13th floor is in progress.
  • Tower-2: False ceiling closing at 1st to 5th floor is in progress.
  • Tower-2: Dry area floor tiling work from 2nd to 14th has completed progressing on 15th floor.
  • Tower-2: Corridor area floor tiling 2nd to 10th floor has completed.
  • Tower-2: Staircase granite work on 1st to 14th floor is in progress.
  • Tower-2: External plaster work on Elevation A, B, C, D is in progress.
  • Tower-2: Wardrobe installation is in progress on 2nd to 4th floor.
  • Tower-2: Kitchen cabinet installation is in progress on 2nd to 3rd floor.
  • Tower-2: Balcony installation is in progress on 2nd to 14th floor.

 

MEP:

 

  • Tower-1: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-1: Light & power wiring up to 15th floor, power cable pulling up to 15th floor.
  • Tower-1: Drainage completed up to 14th floor.
  • Tower-1: water supply up to 15th floor, roof in progress.
  • Tower-1: FCU installation up to 15th floor.
  • Tower-1: Ducting up to 4th floor, in progress up to 10th floor.
  • Tower-1: Chilled water network up to 15th floor,
  • Tower-1: Firefighting network up to 15th floor, Pump room in progress & basement, podiums work is up to 70%.
  • Tower-1: Chillers, FAHU, GRP TANK installed. Piping network in progress.
  • Tower-1: Structural cabling work up to 11th floor.

 

 

  • Tower-2: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-2: Light, power wiring, power cable pulling up to 15th floor completed.
  • Tower-2: Drainage completed up to 10th floor, 11th in progress.
  • Tower-2: water supply up to 15th floor.
  • Tower-2: FCU installation up to 15th floor.
  • Tower-2: Ducting up to 3rd floor, in progress up to 9th floor.
  • Tower-2: Chilled water network up to 15th floor.
  • Tower-2: Firefighting network up to 15th floor, Pump room in progress & basement, podiums work is up to 70%-80%.
  • Tower-2: Structural cabling work up to 11th floor.
2018-09-01

CIVIL:

  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has been completed.
  • Tower-1: Block Work has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tiling work has been completed for all floors.
  • Tower-1: Suspension for false ceiling from 1st to 6th floor has completed.
  • Tower-1: False ceiling closing work on 1st to 6th floor is in progress.
  • Tower-1: Wall primer and stucco 1st to 13th floor is in progress.
  • Tower-1: Wet area floor tiling work from 2nd to 14thfloor has completed, 15th floor is in progress
  • Tower-1: Dry area floor tiling work from 2nd to 13th has completed, 14th and 15th floor is in progress
  • Tower-1: Corridor area floor tiling 2nd to 13th floor has completed
  • Tower-1: External plaster work on Elevation A, B, C, D is in progress
  • Tower-1: Sliding door installation is in progress on 2nd floor.
  • Tower-1: Wardrobe installation is in progress on 2nd to 6th floor.
  • Tower-1: Kitchen cabinet installation is in progress on 2nd to 6th floor.
  • Tower-2: Roof floor waterproofing has been completed.
  • Tower-2: Block Works has been completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tiling work has been completed for all floors.
  • Tower-2: Suspension work for false ceiling 1st to 5th floor has completed.
  • Tower-2: Wall primer and stucco 1stto 13th floor is in progress.
  • Tower-2: False ceiling closing at 1st to 4th floor is in progress.
  • Tower-2: wet area water proofing 13th and 14th floor is in progress.
  • Tower-2: Dry area floor tiling work from 2nd to 11th has completed progressing on 12thfloor.
  • Tower-2: Corridor area floor tiling 2nd to 10th floor has completed.
  • Tower-2: Staircase granite work on 1st to 14th floor is in progress.
  • Tower-2: External plaster work on Elevation A, B, C, D is in progress.

 

MEP:

 

  • Tower-1: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-1: Light & power wiring up to 15th floor, power cable pulling up to 14th floor.
  • Tower-1: Drainage completed up to 14th floor.
  • Tower-1: water supply up to 15th floor
  • Tower-1: FCU installation up to 15th floor.
  • Tower-1: Ducting up to 4th floor, in progress up to 10th floor.
  • Tower-1: Chilled water network up to 15th floor,
  • Tower-1: Firefighting network up to 15th floor, Pump room in progress & basement, podiums works are up to 70%.
  • Tower-1: Chillers, FAHU, GRP TANK installed. Piping network in progress.
  • Tower-1: Structural cabling work up to 9th floor.
  • Tower-2: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-2: Light, power wiring, power cable pulling up to 15th floor completed.
  • Tower-2: Drainage completed up to 9th floor.
  • Tower-2: water supply up to 15th floor.
  • Tower-2: FCU installation up to 15th floor.
  • Tower-2: Ducting up to 3rd floor, in progress up to 7th floor.
  • Tower-2: Chilled water network up to 13th floor, in progress 14th floor & 15th floor.
  • Tower-2: Firefighting network up to 15th floor, Pump room in progress & basement, podiums works are up to 70%.
  • Tower-2: Structural cabling work up to 10th floor.

 

WALKTHROUGH VIDEO

PROJECT LOCATION