JavaScript is off. Please enable to view full site.

Glamz

Check More Updates
Timelapse Video
2018-12-01

  CIVIL WORKS:

  • Landscape area work is in progress.
  • Swimming pool’s testing works in progress.
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has been completed.
  • Tower-1: Block Work has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tiling work has been completed for all floors.
  • Tower-1: Suspension for false ceiling from 1s floor to 15th in dry area (kitchen) and corridor from 2nd to 10th.
  • Tower-1: False ceiling closing work from 1st to 6th floor
  • Tower-1: Wall primer and stucco 1st to 15th floor is in progress.
  • Tower-1: Wet area floor tiling work has been completed for all floors.
  • Tower-1: Dry area floor tiling work has been completed for all floors.
  • Tower-1: Corridor area floor tiling 2nd to 15th floor has completed
  • Tower-1: External plaster work on Elevation A, B, C, D has completed
  • Tower-1: Sliding door installation is in progress on 2nd floor to 8th floor.
  • Tower-1: External painting work on 1st to 15th floor is in progress @ Elevation A, C,E,F
  • Tower-1: Wardrobe installation is in progress on 2nd to 12th floor.
  • Tower-1: Kitchen cabinet installation is in progress on 2nd to 9th floor.
  • Tower-1: wooden door installation is in progress on 2nd and 4th floor.
  • Tower-1: Balcony installation is in progress on 2nd to 15th floor
  • Tower-1: Curtain wall installation is in progress on 1st to 15th floor Elevation A,C,F
  • Tower-2: Roof floor waterproofing has been completed.
  • Tower-2: Block Works has been completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tiling work has been completed for all floors.
  • Tower-2: Suspension work for false ceiling 1st to 15th (kitchen) floor has completed.
  • Tower-2: Wall primer and stucco 1stto 15th floor is in progress.
  • Tower-2: False ceiling closing at 1st to 5th floor is in progress.
  • Tower-2: Dry area floor tiling work has been completed for all floors.
  • Tower-2: Corridor area floor tiling has been completed for all floors.
  • Tower-2: Staircase granite work on 1st to 15th floor is in progress.
  • Tower-2: External plaster work on Elevation A, B, C, D is in progress.
  • Tower-2: Wardrobe installation is in progress on 2nd to 8th floor.
  • Tower-2: Kitchen cabinet installation is in progress on 2nd to 9rd floor.
  • Tower-2: Balcony installation is in progress on 2nd to 14th floor
  • Tower-2: Sliding door installation is in progress on 2nd floor to 8th floor.
  • Tower-2: Curtain wall installation is in progress on 1st to 15th floor Elevation A, B, C, D
  • Tower-2: External plaster work on Elevation A, B, C, D has completed.
  • Tower-2: External painting work on 1st to 15th floor is in progress @ Elevation A, B, C, D.

 

MEP WORKS:

  • Tower-1: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-1: Light & power wiring up to 15th floor, power cable pulling up to 15th floor, roof completed.
  • Tower-1: Drainage completed up to 14th floor, Roof also completed, risers completed.
  • Tower-1: water supply up to 15th floor, roof work completed.
  • Tower-1: FCU installation up to 15th floor.
  • Tower-1: Ducting 90% completed up to 15th floor.
  • Tower-1: Chilled water network up to 15th floor, Roof completed.
  • Tower-1: Fire fighting network up to 15th floor, Pump room in progress & basement ,podiums work 95%
  • Tower-1: Chillers, FAHU, GRP TANK installed. CHW & FAHU piping completed.
  • Tower-1: Structural cabling work up to 15th floor.
  • Tower-1: LPG up to 6th floor.
  • Tower-1: DB termination total 15 floors completed typical, GF & roof in progress
  • Tower-1: Transformer delivered & LV cabling work termination in progress.
  • Tower-1: LV room electrical GF completed 50% in progress.
  • Tower-2: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-2: Light, power wiring, power cable pulling up to 15th floor completed.
  • Tower-2: Drainage completed up to 14th, roof also completed, risers completed.
  • Tower-2: water supply up to 15th floor, roof completed
  • Tower-2: FCU installation up to 15th floor.
  • Tower-2: Ducting in progress up to 15th.
  • Tower-2: Chilled water network up to 15th floor, roof completed.
  • Tower-2: Fire fighting network up to 15th floor, Pump room in progress & basement, podiums work are up to 95%.
  • Tower-2: Structural cabling work up to 15th floor.
  • Tower-2: Chillers, FAHU, GRP TANK installed. CHW & FAHU piping completed.
  • Tower-2: LPG up to 5th floor.
  • Tower-2: DB termination total 15 floors completed typical, GF & roof in progress.
  • Tower-2: Transformer delivered & LV cabling work termination in progress.
  • Tower-2: LV room electrical GF completed 50% in progress.
2018-11-15

CIVIL WORKS:

  • Landscape area work is in progress.
  • Swimming pool’s testing works in progress
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has been completed.
  • Tower-1: Block Work has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tiling work has been completed for all floors.
  • Tower-1: Suspension for false ceiling from 1s floor to 15th in dry area (kitchen) and corridor from 2nd to 10th.
  • Tower-1: False ceiling closing work from 1st to 6th floor
  • Tower-1: Wall primer and stucco 1st to 15th floor is in progress.
  • Tower-1: Wet area floor tiling work has been completed for all floors.
  • Tower-1: Dry area floor tiling work has been completed for all floors.
  • Tower-1: Corridor area floor tiling 2nd to 15th floor has completed
  • Tower-1: External plaster work on Elevation A, B, C, D has completed
  • Tower-1: Sliding door installation is in progress on 2nd floor to 6th floor.
  • Tower-1: External painting work on 1st to 15th floor is in progress @ Elevation A, B, C, D.
  • Tower-1: Wardrobe installation is in progress on 2nd to 12th floor.
  • Tower-1: Kitchen cabinet installation is in progress on 2nd to 9th floor.
  • Tower-1: wooden door installation is in progress on 2nd and 4th floor.
  • Tower-1: Balcony installation is in progress on 2nd to 15th floor
  • Tower-1: Curtain wall installation is in progress on 1st to 15th floor Elevation A, B, C, D
  • Tower-2: Roof floor waterproofing has been completed.
  • Tower-2: Block Works has been completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tiling work has been completed for all floors.
  • Tower-2: Suspension work for false ceiling 1st to 15th (kitchen) floor has completed.
  • Tower-2: Wall primer and stucco 1stto 15th floor is in progress.
  • Tower-2: False ceiling closing at 1st to 5th floor is in progress.
  • Tower-2: Dry area floor tiling work has been completed for all floors.
  • Tower-2: Corridor area floor tiling has been completed for all floors.
  • Tower-2: Staircase granite work on 1st to 15th floor is in progress.
  • Tower-2: External plaster work on Elevation A, B, C, D is in progress.
  • Tower-2: Wardrobe installation is in progress on 2nd to 8th floor.
  • Tower-2: Kitchen cabinet installation is in progress on 2nd to 9rd floor.
  • Tower-2: Balcony installation is in progress on 2nd to 14th floor
  • Tower-2: Sliding door installation is in progress on 2nd floor to th floor.
  • Tower-2: Curtain wall installation is in progress on 1st to 15th floor Elevation A, B, C, D
  • Tower-2: External plaster work on Elevation A, B, C, D has completed
  • Tower-2: External painting work on 1st to 15th floor is in progress @ Elevation A, B, C, D.

MEP WORKS: 

  • Tower-1: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-1: Light & power wiring up to 15th floor, power cable pulling up to 15th floor.
  • Tower-1: Drainage completed up to 14th floor, Roof also completed, risers completed.
  • Tower-1: water supply up to 15th floor, roof work completed.
  • Tower-1: FCU installation up to 15th floor.
  • Tower-1: Ducting in progress up to 15th floor.
  • Tower-1: Chilled water network up to 15th floor, Roof completed.
  • Tower-1: Firefighting network up to 15th floor, Pump room in progress & basement, podiums work 95%
  • Tower-1: Chillers, FAHU, GRP TANK installed. CHW & FAHU piping completed.
  • Tower-1: Structural cabling work up to 15th floor.
  • Tower-1: LPG up to 6th floor.
  • Tower-1: DB termination total 13 floors completed typical.
  • Tower-2: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-2: Light, power wiring, power cable pulling up to 15th floor completed.
  • Tower-2: Drainage completed up to 14th roof also completed, risers completed.
  • Tower-2: water supply up to 15th floor, roof completed
  • Tower-2: FCU installation up to 15th floor.
  • Tower-2: Ducting in progress up to 15th.
  • Tower-2: Chilled water network up to 15th floor, roof completed.
  • Tower-2: Firefighting network up to 15th floor, Pump room in progress & basement, podiums work is up to 95%.
  • Tower-2: Structural cabling work up to 15th floor.
  • Tower-2: Chillers, FAHU, GRP TANK installed. CHW & FAHU piping completed.
  • Tower-2: LPG up to 5th floor.
  • Tower-2: DB termination total 11 floors completed typical.

WALKTHROUGH VIDEO

PROJECT LOCATION