JavaScript is off. Please enable to view full site.

Glamz

Check More Updates
Timelapes Video
2018-07-15
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has been completed.
  • Tower-1: Block Works at has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tiling work on 15th floor is in progress.
  • Tower-1: Suspension for false ceiling from 1st to 6th floor has completed.
  • Tower-1: False ceiling closing work on 1st and 6th is in progress.
  • Tower-1: Wall primer and stucco 1st to 13th floor is in progress.
  • Tower-1: Wet area water proofing work at 10th and 11th floor is in progress.
  • Tower-1: Wet area floor tiling work from 2nd to 7thfloor has completed, 8th floor is in progress
  • Tower-1: Dry area floor tiling work from 2nd to 8th has completed, 9th floor is in progress
  • Tower-1: Corridor area floor tiling 2nd to 6th floor has completed
  • Tower-1: External plaster work on Elevation A, B, C, D is in progress
  • Tower-1: Sliding door installation is in progress on 2nd floor.
  • Tower-1: Wardrobe installation is in progress on 2nd to 4th floor.
  • Tower-2: Roof Plastering has completed.
  • Tower-2: Block Works has been completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tiling work 15th floor is in progress.
  • Tower-2: Suspension work for false ceiling 1st to 5th floor has completed.
  • Tower-2: Wall primer and stucco 1stto 13thfloor is in progress.
  • Tower-2: False ceiling closing at 1st to 4th floor is in progress.
  • Tower-2: wet area water proofing 9th and 10th floor is in progress.
  • Tower-2: Dry area floor tiling work from 2nd to 7th has completed.
  • Tower-2: Corridor area floor tiling 2nd and 5th floor has completed.
  • Tower-2: Staircase granite work on 1st to 14th floor is in progress.
  • Tower-2: External plaster work on Elevation A, B, C, D is in progress.
2018-07-01
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has been completed.
  • Tower-1: Block Works at has been completed for all floors.
  • Tower-1: Plastering work at 15th floor is in progress.
  • Tower-1: Wall Tiling work on 14th floor is in progress
  • Tower-1: Suspension for false ceiling from 1st to 5th floor has completed
  • Tower-1: False ceiling closing work on 1st and 5th is in progress
  • Tower-1: Wall primer and stucco 1st to 11th floor is in progress
  • Tower-1: Wet area water proofing work at 8th to 10th floor is in progress.
  • Tower-1: Wet area floor tiling work on 6th floor is in progress
  • Tower-1: Dry area floor tiling work from 2nd to 6th has completed, 7th floor is in progress
  • Tower-1: Corridor area floor tiling 2nd to 5th floor has completed
  • Tower-1: Staircase granite work on 1st to 14th floor is in progress
  • Tower-1: External plaster work on Elevation A, B is in progress
  • Tower-2: Roof Plastering has completed.
  • Tower-2: Block Works has been completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tiling work 14th floor is in progress.
  • Tower-2: Suspension work for false ceiling 1st to 5th floor has completed.
  • Tower-2: Wall primer and stucco 1stto 11thfloor is in progress.
  • Tower-2: False ceiling closing at 1st to 4th floor is in progress.
  • Tower-2: wet area water proofing 6th and 7th floor is in progress.
  • Tower-2: Dry area floor tiling work from 2nd to 6th has completed, 7th floor is in progress.
  • Tower-2: Corridor area floor tiling 2nd and 5th floor has completed.
  • Tower-2: Staircase granite work on 1st to 14th floor is in progress.
  • Tower-2: External plaster work on Elevation A, B is in progress.

WALKTHROUGH VIDEO

PROJECT LOCATION