2018-05-15
  • DCD and BCC obtained.
  • Water meter chamber construction completed and water connection obtained.
  • DEWA electrical meters installation completed.
  • DEWA water meter installation in progress.
  • Empower Flushing works completed.
  • Testing &commissioning in progress.
  • Aluminum doors & windows installation completed, Final sealant works in progress.
  • External Plaster works 100% completed and final painting in progress.
  • External and Internal painting works completed.
  • Swimming pool landscape and WPC flooring completed.
  • ACP cladding completed.
  • Kitchen installation & Snag Work in progress.
  • Landscape works completed.
  • Basketball and tennis court fencing and flood light installation done.
  • Basketball court sport flooring works completed.
  • Main entrance wall cladding completed and canopy installation completed.
  • Basement car park coating completed and signage’s installation completed.
  • Swimming pool BBQ area Pergola completed, Planter area pergola completed.
  • Installation of Light fittings/Sanitary fittings completed.
  • Installation of landscape lighting in progress and water feature in landscape completed.
  • Main entrance sliding door /Automatic door installed and ACP ceiling for main entrance foyer in completed.
  • Sitting area/party hall painting/main entrance lobby decorative painting completed.
  • Drive way ground floor coating completed.
  • Decorative painting works in corridor in progress.
  • Main access for project completed.
  • Permanent building cleaning equipment installed.
  • Gate barrier installation completed.
  • Snag /De-snag works in progress.
  • Handing over process commenced.
2018-05-01
  • DCD and BCC obtained.
  • Water meter chamber construction completed.
  • DEWA electrical meters installation completed.
  • DEWA water meter installation in progress.
  • Empower Flushing works completed.
  • Testing &commissioning in progress.
  • Aluminum doors & windows installation completed, Final sealant works in progress.
  • External Plaster works 100% completed and final painting in progress.
  • External and Internal painting works completed.
  • Swimming pool landscape and WPC flooring completed.
  • ACP cladding completed.
  • Kitchen installation & Snag Work in progress.
  • Landscape works completed.
  • Basketball and tennis court fencing and flood light installation done.
  • Basketball court sport flooring works completed.
  • Main entrance wall cladding completed and canopy installation completed.
  • Basement car park coating completed and signage’s installation completed.
  • Swimming pool BBQ area Pergola completed, Planter area pergola completed.
  • Installation of Light fittings/Sanitary fittings completed.
  • Installation of landscape lighting in progress and water feature in landscape completed.
  • Main entrance sliding door /Automatic door installed and ACP ceiling for main entrance foyer in completed.
  • Sitting area/party hall painting/main entrance lobby decorative painting completed.
  • Drive way ground floor coating completed.
  • Decorative painting works in corridor in progress.
  • Main access for project completed.
  • Permanent building cleaning equipment installed.
  • Gate barrier installation completed.
  • Snag /De-snag works in progress.