Miraclz

Check More Updates
Timelapes Video
2018-09-15
  • Substructure completed
  • Formwork from ground to podium 1in progress.
  • Core wall casting completed first floor to podium1 level – 100%
  • Columns and shear wall casting completed from first floor to podium 1 floor – 95%
  • Podium 1 floor slab formwork in progress – 45%
  • Podium 1 floor slab casting completion as on date – 20%
  • Shoring beams removal in progress – 80%
2018-09-01
  • Raft casting completed
  • Dewatering stopped.
  • Waterproofing works for retaining wall is 100% completed
  • Retaining wall concrete casting 100% completed
  • GF- First floor 100 % vertical casted.
  • Ramp from Basement to ground floor casting completed.
  • Core wall reinforcement in progress from ground floor to First floor- 90%
  • Ground floor slab concrete casted- 100%
  • Ground floor to Podium 1 Core wall casting completed – 100%
  • Ground floor to Podium 1 Columns casting completed – 38%