2018-10-15

·      Raft casting Completed

·      Ramp from Basement to ground floor casting completed.

·      Core wall casting completed P2 level – 100%

·      Core wall reinforcement completed F1 level – 15%

·      Core wall shuttering completed F1 level – 15%

·      Podium 1 floor slab casting completion as on date – 100%

·      Podium 2 floor slab shuttering completion as on date – 30%

·      Podium 2 floor slab casting completion as on date – 15%

2018-10-01
  • Substructure works 98% completed.
  • retaining wall concrete casting 100% completed
  • Ground floor slab concrete casted- 100%
  • Columns casting completed from first floor to podium 1 floor – 100%
  • Core wall casting completed P1 level  to P2 level – 100%
  • Core wall reinforcement completed P2 level  to 1st floor – 95%
  • Core wall shuttering completed P2 level  to 1st floor – 15%
  • Podium 1 floor slab formwork in progress – 90%
  • Podium 1 floor slab casting completion as on date – 65%