JavaScript is off. Please enable to view full site.

Miraclz

Check More Updates
Timelapse Video
2018-12-01

Ø  Substructure:

    • Raft casting completed
    • Dewatering stopped.
    • Waterproofing works for retaining wall is 100% completed
    • Ground floor slab – 100%
    • Ramp from Basement to ground floor casting completed.

Ø  Floor Slab:  

  • Podium 1 floor slab casting completed – 100%
  • Podium 2 floor slab casting completion – 80%
  • 1st floor slab casting completion – 35%
  • 2nd floor slab formwork – 70%

Ø  Core Wall:

  • Core wall casting completed F3-F4 level – 100%
  • Core wall reinforcement completed F4-F5 level –60%
  • Core wall shuttering completed F4-F5 level – 30%
2018-11-15

Substructure:

  • Raft casting completed
  • Dewatering stopped.
  • Waterproofing works for retaining wall is 100% completed
  • Ground floor slab – 100%
  • Ramp from Basement to ground floor casting completed.

Floor Slab: 

  • Podium 1 floor slab casting completed – 100%
  • Podium 2 floor slab casting completion – 70%
  • 1st floor slab casting completion– 35%

Core Wall: 

  • Core wall casting completed F1-F2 level – 100%
  • Core wall casting completed F2-F3 level – 100%
  • Core wall shuttering in progress and reinforcement completed F3-F4 level – 80

WALKTHROUGH VIDEO

PROJECT LOCATION