Resortz

Check More Updates
Timelapes Video
2018-07-15
  • Water proofing works 98% completed.
  • Swimming pool slab casting done.
  • Ground floor slab 100% casting done.
  • Basement to ground floor Ramp casting completed.

 

  • Block no 3:

o   Raft completed.

o   Retaining wall completed.

o   Columns /Shear walls for second floor to third floor casting in progress- 50% completed.

o   Second floor slab casting completed.

o   First floor attic slab casting completed.

o   Second floor to 3rd floor concrete for columns/ shear wall completed-100%.

o   Third floor form work completed-95%

o   Third floor reinforcement 70 % completed

 

  • Block no 2:

o   Raft completed.

o   Waterproofing for retaining walls completed.

o   Vertical elements first floor to second floor completed.

o   First floor slab 100% concrete casting completed.

o   Second floor 100% concrete casting completed.

o   Second floor to third floor columns concrete casting completed – 100%

o   Third floor formwork in progress- 60 %

 

  • Block no 1:

o   Raft completed

o   Waterproofing for retaining wall completed.

o   First floor 100% concrete casting completed.

o   Second floor 100% concrete casting completed.

o   second floor to third floor columns concrete casting completed.

o   Third floor formwork in progress -20%

2018-07-01
  • Water proofing works 98% completed.
  • Swimming pool slab casting done.
  • Ground floor slab 100% casting done.
  • Basement to ground floor Ramp casting completed.
  • Block no 3:

o   Raft completed.

o   Retaining wall completed.

o   Columns /Shear walls for second floor to third floor casting in progress- 50% completed.

o   Second floor slab casting completed.

o   First floor attic slab casting completed.

o   Second floor column and shear wall formwork in progress.

o   Second floor to 3rd floor reinforcement for columns/ shear wall completed-100%.

 

  • Block no 2:

o   Raft completed.

o   Waterproofing for retaining walls completed.

o   Vertical elements first floor to second floor completed.

o   First floor slab 100% concrete casting completed.

o   Second floor form work and reinforcement completed. DM approved.

 

  • Block no 1:

o   Raft completed

o   Waterproofing for retaining wall complete

o   Second floor slab casting 50% completed

o   First floor to second floor verticals casting completed.

o   Second floor slab reinforcement in progress for 2nd part – 80%

WALKTHROUGH VIDEO

PROJECT LOCATION