Timelapes Video
2018-10-15

Structure:

  • Substructure water proofing works 98% completed.
  • Swimming pool slab casting done.
  • Ground floor slab 100% casting done.
  • Basement to ground floor Ramp casting completed.
  • Block No: 03

o   Raft completed.

o   Retaining wall completed.

o   super structure concrete slab casting – 100% completed

o   Roof to Top roof core walls casting completed – 100%

o   Top Roof slab shuttering completed – 95%

o   Top Roof slab reinforcement works completed – 95%

  • Block No: 02

o   Raft completed.

o   Retaining wall completed.

o   super structure concrete slab casting – 100% completed

o   Roof to Top roof core walls casting completed – 100%

o   Top Roof slab shuttering completed – 15%

  • Block No: 01

o   Raft completed.

o   Retaining wall completed.

o   super structure concrete slab casting – 100% completed

o   Roof to Top roof core walls reinforcement completed – 95%

o   Roof to Top roof core walls shuttering completed – 40%

 

  • Finishing works
  • Block 3:

o   Block work- Basement – 90 % completed

o   Ceiling painting - Basement – 85 % completed

o   Block work- Ground floor-95% completed

o   Plastering - Ground floor- 85% completed

o   Block work- First floor- 90% completed

o   Plastering – First floor – 15% completed

o   Block work- Second floor- 80% completed

o   Block work- Third floor- 35% completed

 

  • Block 2:

o   Block work - Basement – 80 % completed

o   Ceiling painting - Basement – 65 % complete

o   Block work- ground floor-90% completed

o   Plastering - Ground floor- 85% completed

o   Block work- First floor- 90% completed

o   Plastering – First floor – 2% completed

o   Block work- Second floor- 45% completed

o   Block work- Third floor- 20% completed

 

  • Block 1:

o   Block work - Basement – 80 % completed

o   Ceiling painting - Basement – 85 % completed

o   Block work- Ground floor - 90% completed

o   Plastering - Ground floor - 85% completed

o   Block work- First floor - 90% completed

o   Plastering – First floor – 2% completed

o   Block work- Second floor - 50% completed

o   Block work- Third floor- 20% completed

 

  • MEP works:

o   Over all Progress:

o   Basement – High level Plumbing works – Completed 80% 

o   High level HVAC works - Completed 70% 

o   High level FF works - Completed 65%  

o   Ground floor – High level Plumbing and drainage works – Completed 50%  

o   High level HVAC works - Completed 10%  

o   High level FF works - Completed 15%  

o   First floor – High level Plumbing works – In progress  

o   High level HVAC works – In progress  

o   High level FF works – In progress  

2018-10-01

Structure:

  • Substructure works 98% completed.
  • Block no 3:
    • Roof floor slab casting – 100% completed
    • Roof to Top roof core walls casting completed – 100%
    • Top Roof slab shuttering completed – 30%
  • Block no 2:
    • Roof floor slab casting – 100% completed
    • Roof to Top roof core walls reinforcement completed – 75%
    • Roof to Top roof core walls shuttering completed – 25%
  • Block no 1:
    • Roof floor slab casting – 100% completed
    • Roof to Top roof core walls reinforcement completed – 50%
    • Roof to Top roof core walls shuttering completed – 25%

Finishing works:

 

  • Block 3:
    • Block work- Basement – 85 % completed
    • Ceiling painting - Basement – 85 % completed
    • Block work- Ground floor-95% completed
    • Plastering - Ground floor- 65% completed
    • Block work- First floor- 90% completed
    • Plastering – First floor – 15% completed
    • Block work- Second floor- 75% completed
    • Block work- Third floor- 35% completed

 

 

  • Block 2:
    • Block work - Basement – 80 % completed
    • Ceiling painting - Basement – 20 % complete
    • Block work- ground floor-90% completed
    • Plastering - Ground floor- 50% completed
    • Block work- First floor- 90% completed
    • Plastering – First floor – 2% completed
    • Block work- Second floor- 25% completed

 

  • Block 1:
    • Block work - Basement – 80 % completed
    • Ceiling painting - Basement – 80 % completed
    • Block work- Ground floor - 85% completed
    • Plastering - Ground floor - 65% completed
    • Block work- First floor - 90% completed
    • Plastering – First floor – 2% completed
    • Block work- Second floor - 40% completed