2018-11-01

CIVIL Works:

  • Landscape area work is in progress.
  • Swimming pool’s waterproof testing works in progress
  • Window cleaning systems monorail brackets installation in progress.
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has completed.
  • Tower-1: Block work has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tile work has been completed for all floors.
  • Tower-1: False ceiling suspension work from 1st to 7th floor has been
  • Tower-1: False ceiling closing 1st to 7th floor has been completed.
  • Tower-1: Wall primer and stucco has started and progressing well from 1st to 15th
  • Tower-1: Wet area floor tiling work has been completed for all floors.
  • Tower-1: Dry area Tiling work has been completed for all floors.
  • Tower-1: Corridor area floor tiling work has been completed for all floors.
  • Tower-1: Wet area grid work has been completed for all floors (Kitchen)
  • Tower-1: Wet area false ceiling closing is in progress on 2nd to 13th
  • Tower-1: Corridor area false ceiling suspension work 1st to 15th floor is in progress.
  • Tower-1: Corridor area false ceiling closing is in progress on 2nd and 12th
  • Tower-1: Sliding door installation has completed on 2nd to 12th floor and progressing on 13th to 15th
  • Tower-1: Kitchen cabinet installation has completed on 2nd to 13th floor and progressing on 14th & 15th
  • Tower-1: Wardrobe installation has been completed from 2nd to 15th
  • Tower-1: Wooden door installation in progress on 2nd to 9th
  • Tower-1: Mashrabia installation work is in progress @ Elevation B
  • Tower-1: External plastering work has been completed.
  • Tower-1: External painting work on 1st to 15th floor is in progress @ Elevation A, B, C, D.
  • Tower-1: Curtain wall installation work on 1st to 15th floor is in progress @ Elevation A, B, C, D
  • Tower-2: Roof floor water proofing has completed.
  • Tower-2: Block Works has completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tile work has been completed for all floors.
  • Tower-2: False ceiling suspension work on 1st to 8th floor has completed.
  • Tower-2: False ceiling closing from 1st to 8th floor has been completed.
  • Tower-2: wet area floor tiling work has been completed for all floors.
  • Tower-2: wet area false ceiling suspension work has been completed for all floors.
  • Tower-2: wet area false ceiling closing work on 2nd to 12th floor is in progress
  • Tower-2: Dry area Tiling work has completed for all floors.
  • Tower-2: Corridor area floor tiling work has been completed for all floors.
  • Tower-2: Wall primer 1st to 15th floor is in progress.
  • Tower-2: Staircase flooring has been completed for all floors.
  • Tower-2: Ceiling plaster for dry areas on 9th to 15th floor is in progress.
  • Tower-2: Ceiling plaster for balcony from 1st to 15th floor is in progress.
  • Tower-2: Folding door installation in progress on 2nd to 6th
  • Tower-2: Wooden door installation in progress on 2nd to 10th
  • Tower-2: Balcony handrail installation is in progress on 2nd to 15th
  • Tower-2: Sliding door installation is in progress on 2nd to 15th
  • Tower-2: Corridor area false ceiling closing work on 2nd to 11th floor has completed.
  • Tower-2: Wardrobe installation has been completed from 2nd to 15th
  • Tower-2: Kitchen cabinet installation is in progress on 2nd to 14th
  • Tower-2: Internal painting work on 2nd floor is in progress.
  • Tower-2: External plastering work has been completed.
  • Tower-2: External painting work on 1st to 15th floor is in progress @ Elevation A, B, C, D
  • Tower-2: Curtain wall installation work on 1st to 15th floor is in progress @ Elevation A, B, C, D.

MEP Works:

  • Tower-1: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th
  • Tower-1: Light, power wiring, power cable pulling up to 15th floor, roof also completed.
  • Tower-1: water supply up to 15th floor & roof completed.
  • Tower-1: FCU installation up to 15th floor.
  • Tower-1: Ducting up to 15th floor& roof in progress up to 50%.
  • Tower-1: Chilled water network up to 15th floor, roof completed.
  • Tower-1: Firefighting network up to 15th, pump room completed & basement podiums work completed.
  • Tower -1: Structural cabling up to 15th floor.
  • Tower-1: Chillers, FAHU & GRP water tank installation completed, piping network also completed.
  • Tower-1; Fire alarm accessories completed in flats up to 15th floor, corridor in progress.
  • Tower-1: LPG branch piping completed up to 9th floor, Roof progressed 60%.
  • Tower-2: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th
  • Tower-2: Light, power wiring, power cable pulling up to 15th floor, roof also completed.
  • Tower-2: Drainage completed up to 14th floor, roof completed.
  • Tower-2: water supply up to 15th floor & roof completed.
  • Tower-2: FCU installation up to 15th floor.
  • Tower-2: Ducting up to 15th floor, roof completed 50%.
  • Tower-2: Chilled water network up to 15th floor, roof completed.
  • Tower-2: Firefighting network up to 15th, pump room completed & basement podiums work completed.
  • Tower -2: Structural cabling up to 15th
  • Tower-2: Chillers, FAHU & GRP water tank installation completed, piping network also completed.
  • Tower-2: Fire alarm accessories completed in flats up to 15th floor, corridor in progress.
  • Tower-2: LPG branch piping completed up to 8th Roof progressed 60%.
2018-10-15

CIVIL:

  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has completed.
  • Tower-1: Block work has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tile work has been completed for all floors.
  • Tower-1: False ceiling suspension work from 1st to 7th floor has been completed.
  • Tower-1: False ceiling closing 1st to 7th floor has been completed.
  • Tower-1: Wall primer and stucco has started and progressing well from 1st to 15th floor.
  • Tower-1: Wet area floor tiling work has been completed for all floors.
  • Tower-1: Dry area Tiling work has been completed for all floors.
  • Tower-1: Corridor area floor tiling work has been completed for all floors.
  • Tower-1: Wet area grid work has been completed for all floors (Kitchen)
  • Tower-1: Wet area false ceiling closing is in progress on 2nd to 8th floor.
  • Tower-1: Corridor area false ceiling suspension work 1st to 15th floor is in progress.
  • Tower-1: Corridor area false ceiling closing is in progress on 2nd and 8th floor.
  • Tower-1: Sliding door installation has completed on 2nd to 10th floor and progressing on 11th to 15th floor.
  • Tower-1: Kitchen cabinet installation has completed on 2nd to 8th floor and progressing on 9th to 12th floor.
  • Tower-1: Wardrobe installation is in progress on 2nd to 9th floor.
  • Tower-1: Wooden door installation in progress on 2nd to 5th floor.
  • Tower-1: Mashrabia installation work is in progress @ Elevation B
  • Tower-1: External plastering work on 1st to 15th floor is in progress @ Elevation A, B, C, D.
  • Tower-1: External painting work on 1st to 15th floor is in progress @ Elevation A, B, C, D.
  • Tower-1: Curtain wall installation work on 1st to 15th floor is in progress @ Elevation A, B, C, D
  • Tower-2: Roof floor water proofing has completed.
  • Tower-2: Block Works has completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tile work has been completed for all floors.
  • Tower-2: False ceiling suspension work on 1st to 8th floor has completed.
  • Tower-2: False ceiling closing from 1st to 8th floor has been completed.
  • Tower-2: wet area floor tiling work has been completed for all floors.
  • Tower-2: wet area false ceiling suspension work has been completed for all floors.
  • Tower-2: wet area false ceiling closing work on 2nd to 7th floor is in progress
  • Tower-2: Dry area Tiling work has completed for all floors.
  • Tower-2: Corridor area floor tiling work has been completed for all floors.
  • Tower-2: Wall primer 1st to 15th floor is in progress.
  • Tower-2: Staircase flooring has been completed for all floors.
  • Tower-2: Ceiling plaster for dry areas on 9th to 15th floor is in progress.
  • Tower-2: Ceiling plaster for balcony from 1st to 15th floor is in progress.
  • Tower-2: Folding door installation in progress on 2nd to 4th floor.
  • Tower-2: Wooden door installation in progress on 2nd to 9th floor.
  • Tower-2: Balcony handrail installation is in progress on 2nd to 15th floor.
  • Tower-2: Sliding door installation is in progress on 2nd to 14th floor.
  • Tower-2: Corridor area false ceiling closing work on 2nd to 8th floor has completed.
  • Tower-2: Wardrobe installation is in progress on 2nd to 13th floor.
  • Tower-2: Kitchen cabinet installation is in progress on 2nd to 10th floor.
  • Tower-2: Internal painting work on 2nd floor is in progress.
  • Tower-2: External plastering work on 1st to 15th floor is in progress @ Elevation A, B, C, D.
  • Tower-2: External painting work on 1st to 15th floor is in progress @ Elevation A, B, C, D
  • Tower-2: Curtain wall installation work on 1st to 15th floor is in progress @ Elevation A, B, C, D.

MEP

  • Tower-1: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-1: Light, power wiring, power cable pulling up to 15th floor, roof also completed.
  • Tower-1: water supply up to 15th floor & roof.
  • Tower-1: FCU installation up to 15th floor.
  • Tower-1: Ducting up to 15th floor & roof in progress.
  • Tower-1: Chilled water network up to 15th floor, roof completed.
  • Tower-1: Firefighting network up to 15th, pump room completed & basement podiums work completed.
  • Tower -1: Structural cabling up to 15th floor.
  • Tower-1: Chillers, FAHU & GRP water tank installation completed, piping network also completed.
  • Tower-1; Fire alarm accessories completed in flats up to 15th floor, corridor in progress.
  • Tower-1: LPG branch piping completed up to 6th floor.
  • Tower-2: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-2: Light, power wiring, power cable pulling up to 15th floor, roof also completed.
  • Tower-2: Drainage completed up to 14th floor, roof in progress 90%.
  • Tower-2: water supply up to 15th floor & roof.
  • Tower-2: FCU installation up to 15th floor.
  • Tower-2: Ducting up to 15th floor, roof in progress.
  • Tower-2: Chilled water network up to 15th floor, roof completed.
  • Tower-2: Firefighting network up to 15th, pump room completed & basement podiums work completed.
  • Tower -2: Structural cabling up to 15th floor.
  • Tower-2: Chillers, FAHU & GRP water tank installation completed, piping network also completed.
  • Tower-2: Fire alarm accessories completed in flats up to 15th floor, corridor in progress.
  • Tower-2: LPG branch piping completed up to 6th floor.