Starz

Check More Updates
Timelapes Video
2018-04-15

·Interlock work @ Basement in progress" >

  • · Tower-1: Upper Roof floor reinforcement for column work is in progress.
  • · Tower-1: Block Works at 14th floor is in progress.
  • · Tower-1: Plastering work at 11th and 12th floor is in progress.
  • · Tower-1: Wall Tiling work is progressing well on 8th and 10th floor.
  • · Tower-1: False ceiling suspension work on 1st to 7th floor is in progress.
  • · Tower-1: False ceiling closing 1st and 2nd in progress
  • · Tower-1: wall primer and stucco 1st to 7th floor is in progress.
  • · Tower-1: Water proofing for wet area 4th floor is in progress.
  • · Tower-1: Dry area Tiling 2nd, 3rd floor in progress.
  • · Tower-2: Upper Roof Slab is in progress. Roof parapet reinforcement & shuttering progress
  • · Tower-2: Block Works at 15th floor is in progress.
  • · Tower-2: Plastering work at 10th to 12th floor is in progress.
  • · Tower-2: Wall Tile work 10th floor is in progress.
  • · Tower-2: False ceiling suspension 1st to 8th in progress.
  • · Tower-2: Water proofing for wet area on 5th floor is in progress.
  • · Tower-2: wet area floor tiling 4th floor is in progress.
  • · Tower-2: Dry area Tiling 4th floor in progress.
  • · Tower-2: Corridor area Tiling work on 2nd floor is in progress.
  • · Tower-2: wall primer 1st to 9th floor is in progress.
  • · Tower-2: staircase flooring 2nd to 3rd  floor in progress.
  • · Tower-2: Ceiling plaster for dry areas on 9th floor is in progress.
  • · Tower-2: Ceiling plaster for balcony 1st to 9th floor is in progress.
  • · Spray plaster of ceiling fine and texture @ podium-2 in progress
  • · Spray plaster texture work on ceiling @ Basement and Podium -1 in progress
  • · Interlock work @ Basement in progress

 

MEP STATUS– STARZ (TOWER –A)

ELECTRICAL:

  • Wall conduit & DB Fixing- completed up to 12th floor.
  • POWER WIRING- upto 2nd floor
  • Emergency & Exit & Fire alarm wiring – completed up to 10th floor.
  • Lights wiring - completed up to 5th floor.
  • Structural cabling- upto 2nd floor.

 

PLUMBING:

  • Drainage – Upto 11th Floor.
  • Drainage Riser – Up To 11th Floor In Progress
  • Water Supply PPR – 7th Floor In Progress
  • Water Supply PEX & Wall Drain – Completed Up To 12th Floor.

 

FIRE FIGHTING:

  • MAINLINE – 7th floor in progress
  • BRANCHES – 6th in progress.
  • RISER – done up to 5th floor.

 

HVAC:

  • FCU- 1ST TO 11TH floor.
  • DUCTING – 1st & 2nd in progress.

 

CHILLER PIPING:

  • MAINLINE –5th floor in progress.
  • BRANCHES – 5th floor in progress.

 

STARZ SUBSTATION IS APPROVED.

 

MEP STATUS– STARZ (TOWER –B)

ELECTRICAL:

  • Wall conduit & DB Fixing- up to 13th floor, 14th  in progress.
  • Emergency & Exit & Fire alarm wiring – up to 10th floor
  • Lights wiring – up to 6th floor.
  • POWER WIRING- up to 6th  floor
  • Structural cabling- up to 3rd floor.

 

PLUMBING:

  • DRAINAGE high-level – up to 9th floor.
  • DRAINAGE RISER – up to 10th floor completed.
  • WATER SUPPLY PPR – up to 7th floor, 8th in progress.
  • WATER SUPPLY PEX & WALL DRAIN – up to 13th floor, 14th in progress.

 

FIRE FIGHTING:

  • MAINLINE –up to 7th floor.
  • BRANCHES – 7th in progress
  • RISER – up to 6th floor

 

HVAC:

  • FCU- 1ST TO 13TH floor
  • DUCTING – 1st & 2nd in progress.

 

CHILLER PIPING:

  • MAINLINE – 8th floor in progress
  • BRANCHES- 7th floor in progress
2018-04-01
  • Tower-1: Roof floor slab shuttering work is in progress.
  • Tower-1: Block Works at 13th floor is in progress.
  • Tower-1: Plastering work at 8th and 10th floor is in progress.
  • Tower-1: Wall Tiling work is progressing well on 8th floor.
  • Tower-1: False ceiling suspension work on 1st to 7th floor is in progress.
  • Tower-1: wall primer 1st to 7th floor is in progress.
  • Tower-1: Water proofing for wet area 2nd and 3rd  is in progress.
  • Tower-1: Dry area Tiling 2nd floor in progress.
  • Tower-2: Upper Roof Slab is in progress.
  • Tower-2: Block Works at 14th floor above Lintel Level is in progress.
  • Tower-2: Block Works at 13th floor above Lintel Level is in progress.
  • Tower-2: Plastering work at 8th to 11th floor is in progress.
  • Tower-2: Wall Tile work 8th, 9th and 10th floor is in progress.
  • Tower-2: False ceiling suspension 1st to 8th in progress.
  • Tower-2: Water proofing for wet area 1st and 2ndfloor is in progress.
  • Tower-2: Water proofing for wet area on 4th floor is in progress.
  • Tower-2: wet area floor tiling 1st to 3rd floor is in progress.
  • Tower-2: Dry area Tiling 2nd and 3rd floor in progress.
  • Tower-2: Corridor area Tiling work on 2nd floor is in progress.
  • Tower-2: wall primer 1st to 9th floor is in progress.
  • Tower-2: staircase flooring 2nd to 3rd  floor in progress.
  • Tower-2: Ceiling plaster for dry areas on 9th floor is in progress.
  • Tower-2: Ceiling plaster for balcony 1st to 4th floor is in progress.

WALKTHROUGH VIDEO

PROJECT LOCATION