Starz

Check More Updates
Timelapes Video
2018-06-01
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has completed.
  • Tower-1: Block works has been completed for all floors.
  • Tower-1: Plastering work at 14th floor is in progress.
  • Tower-1: Wall Tile work is in progress on 13th floor.
  • Tower-1: False ceiling suspension work from 1st to 7th floor has been completed.
  • Tower-1: False ceiling closing 1st to 5th floor is in progress.
  • Tower-1: Wall primer and stucco has started and progressing well from 1st to 12th floor.
  • Tower-1: Water proofing for wet area is in progress on 7th floor.
  • Tower-1: wet area floor tiling work is in progress on 5th floor.
  • Tower-1: Dry area Tiling work has completed on 2nd to 4th floor and progressing on 5th floor.
  • Tower-1: Corridor area Tiling work progressing on 2nd and 3rd floor.
  • Tower-1: Wet area grid work 1st and 2nd floor is in progress.  
  • Tower-1: Corridor area false ceiling suspension work 1st and 2nd floor is in progress.
  • Tower-2: Roof floor water proofing has completed.
  • Tower-2: Block Works has completed for all floors.
  • Tower-2: Internal plastering work has been completed till 14th Floor and progressing on 15th floor.
  • Tower-2: Wall Tile work is in progress on 14th floor.
  • Tower-2: False ceiling suspension work on 1st to 8th floor has completed.
  • Tower-2: False ceiling closing 1st to 8th floor is in progress.
  • Tower-2: Water proofing for wet area on 9th and 10th floor is in progress.
  • Tower-2: wet area floor tiling work is in progress on 7th floor.
  • Tower-2: wet area false ceiling suspension work on 1st and 2nd floor is in progress.
  • Tower-2: wet area false ceiling closing work on 2nd floor is in progress
  • Tower-2: Dry area Tiling work 8thfloor is in progress.
  • Tower-2: Corridor area Tiling work on 2nd and 3rd floor has completed, 4th and 5th floor is in progress.
  • Tower-2: wall primer 1st to 12th floor is in progress.
  • Tower-2: staircase flooring 7th to 9thfloor is in progress.
  • Tower-2: Ceiling plaster for dry areas on 9th to 13th floor is in progress.
  • Tower-2: Ceiling plaster for balcony from 1st to 13th floor is in progress.
  • Tower-2: Folding door installation in progress on 2nd to 4th floor.
  • Tower-2: Wooden door installation in progress on 2nd floor.
  • Tower-2: Balcony handrail installation is in progress on 2nd floor.
  • Tower-2: Sliding door installation is in progress on 2nd floor.
  • Tower-2: Corridor area false ceiling closing work on 2nd floor has completed.
  • Tower-2: Internal painting work on 2nd floor is in progress.
  • Tower-2: External plastering work on 1st to 12th floor is in progress @ Elevation A, D.
  • Tower-2: Curtain wall installation work on 1st to 2nd floor is in progress @ Elevation A, D.
2018-05-15
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has started.
  • Tower-1: Block works at 15th floor is in progress.
  • Tower-1: Plastering work at 12thfloor and 13th floor is in progress.
  • Tower-1: Wall Tile work is in progress on 11th and 12th floor.
  • Tower-1: False ceiling suspension work on 1st to 7th floor is in progress.
  • Tower-1: False ceiling closing 1st to 4th floor is in progress.
  • Tower-1: Wall primer and stucco has started and progressing well from 1st to 11th floor.
  • Tower-1: Water proofing for wet area is in progress on 6th and 7th floor.
  • Tower-1: Dry area Tiling work has completed on 2nd to 4th floor and progressing on 5th floor.
  • Tower-2: Roof floor water proofing has completed.
  • Tower-2: Block Works has completed.
  • Tower-2: Internal plastering work has been completed till 13th Floor and progressing on 14th floor.
  • Tower-2: Wall Tile work is in progress on 12th floor.
  • Tower-2: False ceiling suspension work is in progress from 1st to 8th floor.
  • Tower-2: False ceiling closing 1st to 6th floor is in progress.
  • Tower-2: Water proofing for wet area on 7th and 8th floor is in progress.
  • Tower-2: wet area floor tiling work is in progress on 6th floor.
  • Tower-2: Dry area Tiling work 5th and 6thfloor in progress.
  • Tower-2: Corridor area Tiling work on 2nd and 3rd floor has completed
  • Tower-2: wall primer 1st to 11th floor is in progress.
  • Tower-2: staircase flooring 2nd to 3rdfloor in progress.
  • Tower-2: Ceiling plaster for dry areas on 9th to 11th floor is in progress.
  • Tower-2: Ceiling plaster for balcony from 1st to 11th floor is in progress.
  • Tower-2: Folding door installation in progress on 2nd floor.
  • Tower-2: Wooden door installation in progress on 2nd floor.
  • Tower-2: Balcony handrail installation is in progress on 2nd floor.
  • Tower-2: Sliding door installation is in progress on 2nd floor.