PROGRESS ( 31-May-2023 )

Excavation
100%
Shoring
100%
Concrete
100%
Blockwork
100%
Internal Plaster
100%
Electrical
89%
Hvac
85%
Glass Aluminium
88%
Wooden doors
85%
Wardrobe
85%
Kitchen
85%
Plumbing
92%
External Plaster
100%
Internal Paint
99.5%
External Paint
80%
Tiling Marble
95%
Mechanical
87.5%
Handrail Fencing
92%
False ceiling
85%
Lighting
75%
Bath sanitary
75%