Bayz

Check More Updates
Timelapse Video
2019-02-16
  • DM Building permit obtained.
  • Main contractor commenced works.
  • LIFT PIT blinding concrete casted.
  • LIFT pit sacrificial block work in progress.
  • Compaction for pile cap, works in progress.
  • Site mobilization in progress.
  • Lift pit raft concrete casting in progress.
  • Water proofing works for Raft in progress. Zone 1 & 2
  • Tower crane 1 erection completed.
  • Lift pit area core wall casted till Basement 2 level.
  • Reinforcement works for raft in progress in Zone 1 and zone 2 in progress.
  • Sump pit block work and waterproofing in progress.
  • Backfilling for lift pit area blinding and waterproofing in progress.
  • Compaction and Blinding works in progress in Zone 3.
2019-02-01
  • Guide wall work has been completed.
  • Soil excavation work has started and completed till platform level.
  • Shoring & Piling work has started and completed 194 No’s of soft piles.
  • Shoring & piling work has started and completed 194No’s of hard piles.
  • Capping beam completed.
  • Concrete panel for shoring completed.
  • DM Building permit obtained.
  • Main contractor commenced works.
  • LIFT PIT blinding concrete casted.
  • LIFT pit sacrificial block work in progress.
  • Compaction for pile cap, works in progress.
  • Site mobilization in progress.
  • Lift pit raft concrete casting in progress.
  • Water proofing works for Raft in progress. Zone 1 & 2
  • Tower crane foundation in progress.
  • Reinforcement works for raft in progress in Zone 1
  • Compaction and Blinding works in progress in Zone 2