Jewelz

Check More Updates
2019-02-16
  • Main Contractor, Site Mobilization and office setup completed.
  • Shoring works completed - 100%.
  • Excavation completed - 100%
  • Road base filling and compaction 100% completed.
  • Blinding concrete (P.C.C.) in progress- 98%
  • Waterproofing work for raft is in progress - 98%
  • Waterproofing protection screed completed - 95 %
  • Raft rebar work is in progress - 65%
  • Water tanks raft casting completed 100%
  • Water tank wall rebar work is in progress- 20%
  • One Tower crane installation done and working.
  • Drainage manhole work under raft is in progress.
2019-02-01
  • Main Contractor, Site Mobilization and office setup completed.
  • Shoring drawing/design approved and Shoring works in progress- 100%
  • Excavation completed 100%
  • Road base filling and compaction completed - 98%.
  • Blinding concrete (P.C.C.) in progress- 96%
  • Waterproofing work for raft is in progress - 90%
  • Waterproofing protection screed completed - 80 %
  • MEP contractor appointment under finalization.
  • Raft rebar work is in progress - 20%
  • one Tower crane installation done.
  • Back filling for shoring work completed.
  • Raft block work is in progress - 96%