JavaScript is off. Please enable to view full site.

Glamz

Check More Updates
Timelapse Video
2019-02-16

CIVIL WORKS:

  • Landscape area soiling work is in progress.
  • Swimming pool’s testing works are in progress.
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has been completed.
  • Tower-1: Block Work has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tiling work has been completed for all floors.
  • Tower-1: Suspension for false ceiling from 1st to 15th floor in dry areas, and corridor areas from 2nd to 10th floor have been completed.
  • Tower-1: False ceiling closing work is in progress from 1st to 8th  floor.
  • Tower-1: Wall primer and stucco 1st to 15th floor is in progress.
  • Tower-1: Wet area floor tiling work has been completed for all floors.
  • Tower-1: Dry area floor tiling work has been completed for all floors.
  • Tower-1: Corridor area floor tiling from 1st to 15th floor has been completed.
  • Tower-1: External plaster work on Elevation A, B, C, D has been completed.
  • Tower-1: Sliding door installation is completed till 12th floor and is in progress from 13 to 15th floor.
  • Tower-1: Folding door installation is in progress from 1st to 9th floor.
  • Tower-1: External painting work from 1st to 15th floor is in progress @ Elevation A,C,E,F.
  • Tower-1: Wardrobe installation is in progress from 1st to 15th floor.
  • Tower-1: Kitchen cabinet installation is in progress from 1st to 15th floor.
  • Tower-1: wooden door installation is in progress from 2nd to 6th floor.
  • Tower-1: Balcony installation is in progress from 2nd to 15th floor
  • Tower-1: Curtain wall installation is in progress from 1st to 15th floor Elevation A,C,F.
  • Tower-2: Roof floor waterproofing has been completed.
  • Tower-2: Block Works have been completed on all floors.
  • Tower-2: Internal plastering work has been completed on all floors.
  • Tower-2: Wall Tiling work has been completed on all floors.
  • Tower-2: Suspension work for false ceiling 1st to 15th (kitchen) floor has completed.
  • Tower-2: Wall primer and stucco from 1st to 15th floor is in progress.
  • Tower-2: False ceiling closing from 1st to 6th floor is in progress.
  • Tower-2: Dry area floor tiling work has been completed for all floors.
  • Tower-2: Corridor area floor tiling has been completed for all floors.
  • Tower-2: Staircase granite work has completed for all floors.
  • Tower-2: External plaster work on Elevation A, B, C, D is in progress.
  • Tower-2: Wardrobe installation is in progress from 1st to 15th floor.
  • Tower-2: Kitchen cabinet installation is in progress from 1st to 15th floor.
  • Tower-2: Balcony installation is in progress from 2nd to 14th floor.
  • Tower-2: Sliding door installation is in progress from 2nd to 14th floor.
  • Tower-2: Folding door installation is in progress from 1st to 8th floor.
  • Tower-2: Curtain wall installation is in progress from 1st to 15th floor Elevation A, B, C, D
  • Tower-2: External plaster work on Elevation A, B, C, D has been completed.
  • Tower-2: External painting work from 1st to 15th floor is in progress @ Elevation A, B, C, D.

 

MEP Works:

 

  • Tower-1: 1st fix wall conduits & plumbing PEX Pipes have been completed up to 15th floor.
  • Tower-1: Light and power cable pulling up to roof has been completed.
  • Tower-1: Drainage network is completed on all typical floors and is in progress at Podium 2.
  • Tower-1: Water supply installation has been completed up to roof floor.
  • Tower-1: FCU installation has been completed up to 15th floor.
  • Tower-1: Installation of Ducts has been completed up to 90% in all typical floors.
  • Tower-1: Riser ducts completed up to 11th floor & is under progress from 12th to 15th floors.
  • Tower-1: Chilled water network has been completed up to roof floor.
  • Tower-1: Fire-fighting network has been completed in all floors.
  • Tower-1: Fire Fighting Pump room installation works in progress in basement.
  • Tower-1: 30 of 60 Fire Hose Reel Cabinets have been installed in all typical.
  • Tower-1: Chillers, FAHU & GRP water tank have been installed along with their piping network.
  • Tower-1: Structural cabling works are in progress on all floors.
  • Tower-1: LPG branch piping works completed up to 7th floor.
  • Tower-1: DB termination in all typical floors have been completed & are in progress in Ground and Roof Floors.
  • Tower 1: Sub-Main Distribution Panel has been installed till the 10th floor and is under progress from 11th – 15th floor.
  • Tower-1: Transformers have been delivered & LV cable termination activities in progress.
  • Tower-1: Panel installation and Cable Termination in LV room has progressed to 70%.
  • Tower 1: HV cable pulling and termination to transformer from DEWA has been completed.
  • Tower-2: 1st fix wall conduits & plumbing PEX Pipes completed up to 15th floor.
  • Tower-2: Light and power cable pulling up to roof has been completed.
  • Tower-2: Drainage network is completed on all typical floors and is in progress at Podium 2.
  • Tower-2: Water supply installation has been completed up to roof floor.
  • Tower-2: FCU installation has been completed up to 15th floor.
  • Tower-2: Installation of Ducts has been completed up to 90% in all typical floors.
  • Tower-2: Chilled water network has been completed up to roof floor.
  • Tower-2: Fire-fighting network has been completed in all floors.
  • Tower-2: Fire Fighting Pump room installation works are under progress in basement.
  • Tower-2: Chillers, FAHU & GRP water tank have been installed along with their piping network.
  • Tower-2: Structural cabling works are in progress on all floors.
  • Tower-2: LPG branch piping works completed up to 6th floor.
  • Tower-2: DB termination in all typical floors have been completed & are in progress in Ground and Roof Floors.
  • Tower-2: Sub-Main Distribution Panel has been installed till the 8th floor and is under progress from the 9th floor.
  • Tower 2: HV cable pulling and termination to transformer from DEWA has been completed.
2019-02-01

CIVIL WORKS:

  • Landscape area work is in progress.
  • Swimming pool’s testing works in progress.
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has been completed.
  • Tower-1: Block Work has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tiling work has been completed for all floors.
  • Tower-1: Suspension for false ceiling from 1st to 15th floor in dry area (kitchen) and corridor from 2nd to 10th floor has completed.
  • Tower-1: False ceiling closing work is in progress from 1st to 7th floor
  • Tower-1: Wall primer and stucco 1st to 15th floor is in progress.
  • Tower-1: Wet area floor tiling work has been completed for all floors.
  • Tower-1: Dry area floor tiling work has been completed for all floors.
  • Tower-1: Corridor area floor tiling 1st to 15th floor has completed
  • Tower-1: External plaster work on Elevation A, B, C, D has completed
  • Tower-1: Sliding door installation is in progress on 2nd to 14th floor.
  • Tower-1: Folding door installation is in progress on 1st to 8th floor.
  • Tower-1: External painting work on 1st to 15th floor is in progress @ Elevation A, C,E,F
  • Tower-1: Wardrobe installation is in progress on 1st to 15th floor.
  • Tower-1: Kitchen cabinet installation is in progress on 1st to 15th floor.
  • Tower-1: wooden door installation is in progress on 2nd to 6th floor.
  • Tower-1: Balcony installation is in progress on 2nd to 15th floor
  • Tower-1: Curtain wall installation is in progress on 1st to 15th floor Elevation A,C,F
  • Tower-2: Roof floor waterproofing has been completed.
  • Tower-2: Block Works has been completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tiling work has been completed for all floors.
  • Tower-2: Suspension work for false ceiling 1st to 15th (kitchen) floor has completed.
  • Tower-2: Wall primer and stucco from 1st to 15th floor is in progress.
  • Tower-2: False ceiling closing at 1st to 5th floor is in progress.
  • Tower-2: Dry area floor tiling work has been completed for all floors.
  • Tower-2: Corridor area floor tiling has been completed for all floors.
  • Tower-2: Staircase granite work has completed for all floors.
  • Tower-2: External plaster work on Elevation A, B, C, D is in progress.
  • Tower-2: Wardrobe installation is in progress on 1st to 15th floor.
  • Tower-2: Kitchen cabinet installation is in progress on 1st to 15th floor.
  • Tower-2: Balcony installation is in progress on 2nd to 14th floor.
  • Tower-2: Sliding door installation is in progress on 2nd to 13th floor.
  • Tower-2: Folding door installation is in progress on 1st to 7th floor.
  • Tower-2: Curtain wall installation is in progress on 1st to 15th floor Elevation A, B, C, D
  • Tower-2: External plaster work on Elevation A, B, C, D has completed.
  • Tower-2: External painting work on 1st to 15th floor is in progress @ Elevation A, B, C, D.

MEP WORKS:

  • Tower-1: 1st fix wall conduits & plumbing PEX Pipes completed up to 15th floor.
  • Tower-1: Light and power cable pulling up to roof has been completed.
  • Tower-1: Drainage network is completed on all typical floors and is in progress at Podium 2
  • Tower-1: Water supply installation has been completed up to roof floor
  • Tower-1: FCU installation has been completed up to 15th floor.
  • Tower-1: Installation of Ducts has been completed up to 90% in all typical floors
  • Tower-1: Riser ducts completed up to 10th floor & is under progress from 11th to 15th floors
  • Tower-1: Chilled water network has been completed up to roof floor
  • Tower-1: Fire-fighting network has been completed in all floors
  • Tower-1: Fire Fighting Pump room installation works in progress in basement
  • Tower-1: 30 of 60 Fire Hose Reel Cabinets have been installed in all typical
  • Tower-1: Chillers, FAHU & GRP water tank has been installed along with its piping network
  • Tower-1: Structural cabling works are in progress on all floors
  • Tower-1: LPG branch piping works completed up to 7th floor.
  • Tower-1: DB termination in all typical floors have been completed & are in progress in Ground and Roof Floors.
  • Tower 1: Sub-Main Distribution Panel has been installed till the 9th floor and is under progress from the 10th floor.
  • Tower-1: Transformers have been delivered & LV cable termination activities in progress.
  • Tower-1: Panel installation and Cable Termination in LV room has progressed to 70%.
  • Tower 1: HV cable pulling and termination to transformer from DEWA has been completed
  • Tower-2: 1st fix wall conduits & plumbing PEX Pipes completed up to 15th floor.
  • Tower-2: Light and power cable pulling up to roof has been completed.
  • Tower-2: Drainage network is completed on all typical floors and is in progress at Podium 2
  • Tower-2: Water supply installation has been completed up to roof floor
  • Tower-2: FCU installation has been completed up to 15th floor.
  • Tower-2: Installation of Ducts has been completed up to 90% in all typical floors
  • Tower-2: Chilled water network has been completed up to roof floor
  • Tower-2: Fire-fighting network has been completed in all floors
  • Tower-2: Fire Fighting Pump room installation works in progress in basement
  • Tower-2: Chillers, FAHU & GRP water tank has been installed along with its piping network
  • Tower-2: Structural cabling works are in progress on all floors
  • Tower-2: LPG branch piping works completed up to 6th floor.
  • Tower-2: DB termination in all typical floors have been completed & are in progress in Ground and Roof Floors.
  • Tower-2: Sub-Main Distribution Panel has been installed till the 8th floor and is under progress from the 9th floor.
  • Tower 2: HV cable pulling and termination to the transformer from DEWA has been completed

WALKTHROUGH VIDEO

PROJECT LOCATION