Danube Properties Development LLC Danube Properties Development LLC 8005757 info@danubeproperties.ae

Olivz by Danube

Check More Updates
2021-08-31
  • TIS approval work in progress.
  • Dewatering in progress.
  • All Concrete pile are casted 100%
  • Concrete panels for shoring panels Completed
  • Excavation for basement 35 % work in progress.
  • Capping beam casting - 100% Completed
2021-07-31
  • Shoring permit obtained for the project .
  • Enabling works mobilization done .
  • All Machinery and Equipment for excavation mobilized
  • Test bore has been done .
  • TIS approval work in progress.
  • Dewatering works in progress
  • Soft piles total 151/158no’s in progress. Hard pile 138/158
  • Steel I beams delivery to site in progress
  • Concrete panels for shoring panels preparation in progress.
  • Excavation for basement 34% in progress
  • Capping beam casting 64% work in progress.