Resortz

Check More Updates
Timelapse Video
2019-03-31

Finishing Works: 

 

  • Block work:
    • Ground floor- 99%
    • First floor- 99%
    • Second floor- 99%
    • Third floor- 99%
    • Fourth floor-99%

 

  • Plaster:
    • Ground floor-98%
    • First floor- 98%
    • Second floor-98%
    • Third floor- 98%
    • Fourth floor-97%
    • Roof- 98% 

 

  • Tiling:
    • Ground floor- 75%
    • First floor- 94%
    • Second floor -94%
    • Third floor - 93%
    • Fourth floor-  92%

 

  • Paint:
    • Basement - 90% 
    • Ground floor-40%
    • First floor- 45%
    • Second floor – 45%
    • Third floor – 35%
    • Fourth floor – 35%

 

  • Joinery Work:
    • Wardrobe installation completion - 30%
    • Kitchen cabinet installation completion – 15%
    • Folding door installation completion – 60%
    • Sliding door installation completion – 26%

 

 

MEP works:

 

  • Basement       –   over all work completion – 85%
  • Ground floor   –   over all work completion - 90%
  • First floor        – overall work completion - 90%
  • Second floor   – overall work completion - 90%
  • Third floor     – overall work completion - 75%
  • Fourth floor   - overall work completion- 65%
2019-03-15

Finishing Works: 

 

  • Block work:
    • Ground floor- 98%
    • First floor- 98%
    • Second floor- 98%
    • Third floor- 98%
    • Fourth floor-98%

 

  • Plaster:
    • Ground floor-98%
    • First floor- 98%
    • Second floor-98%
    • Third floor- 98%
    • Fourth floor-97%
    • Roof- 98% 

 

  • Tiling:
    • Ground floor- 75%
    • First floor- 92%
    • Second floor -92%
    • Third floor - 90%
    • Fourth floor-  85%

 

  • Paint:
    • Basement - 90% 
    • Ground floor-30%
    • First floor- 30%
    • Second floor – 25%
    • Third floor – 20%
    • Fourth floor – 20%

 

  • Joinery Work:
    • Wardrobe installation completion - 17%
    • Kitchen cabinet installation completion  – 2%.

 

  • Aluminium work:
    • Folding door installation completion – 28%
    • Sliding door installation completion – 5%

 

MEP works:

 

  • Basement       –   over all work completion – 85%
  • Ground floor   –   over all work completion - 90%
  • First floor        – overall work completion - 90%
  • Second floor   – overall work completion - 85%
  • Third floor     – overall work completion - 70%
  • Fourth floor   - overall work completion- 60%