Resortz

Check More Updates
Timelapse Video
2019-02-16

Finishing Works: 

 

  • Block work:
    • Ground floor- 98%
    • First floor- 98%
    • Second floor- 98%
    • Third floor- 98%
    • Fourth floor-97%

 

  • Plaster:
    • Ground floor-97%
    • First floor- 97%
    • Second floor-97%
    • Third floor- 95%
    • Fourth floor-90%
    • Roof- 92% 

 

  • Tiling:
    • Ground floor- 70%
    • First floor- 80%
    • Second floor -80%
    • Third floor - 75%
    • Fourth floor-  65%

 

  • Paint:
    • Basement - 90% 
    • Ground floor- 15%
    • First floor- 15%
    • Second floor – 10%

 

MEP works:

 

  • Basement       –   over all work completion – 80%
  • Ground floor   –   over all work completion - 85%
  • First floor        – overall work completion - 85%
  • Second floor   – overall work completion - 75%
  • Third floor     – overall work completion - 40%
  • Fourth floor   - overall work completion- 30%
2019-02-01

Finishing Works: 

  • Block work:
    • Ground floor- 98%
    • First floor- 98%
    • Second floor- 98%
    • Third floor- 98%
    • Fourth floor-95%
  • Plaster:
    • Ground floor-97%
    • First floor- 95%
    • Second floor-90%
    • Third floor- 75%
    • Fourth floor-75%
    • Roof- 90% 
  • Tiling:
    • Ground floor- 70%
    • First floor- 80%
    • Second floor -65%
    • Third floor - 40%
    • Fourth floor- 7%
  • Paint:
    • Basement - 90% 
    • Ground floor- 10%
    • First floor- 10%

MEP works:

  • Basement  – overall work completion – 80%
  • Ground floor –  overall work completion - 85%
  • First floor  – overall work completion - 85%
  • Second floor – overall work completion - 70%
  • Third floor   – overall work completion - 35%
  • Fourth floor- overall work completion- 25%