Jewelz

Check More Updates
Timelapse Video
2019-04-30
  • Concrete casting for P1 slab   is completed – 100%
  • Shoring beam and precast panel removing work completed -100%
  • Concrete casting for P1-P2 vertical is completed – 100%
  • Formwork for P2 Slab is completed – 100%
  • Reinforcement work for P2 slab in progress – 90%
  • Post tension work for P2 slab in progress – 85%
  • MEP work for P2 slab in progress – 85%
  • Concrete casting of P2 slab in progress – 80%.
  • Deshuttering work of P1 slab soffit in progress – 80%
  • Grouting work for PT of P1 slab is completed – 100%
  • Reinforcement work for P2-L1 vertical in progress – 55%
  • MEP work for P2-L1 vertical in progress – 35%
  • Formwork for P2-L1 vertical in progress – 15%
  • Concrete casting work for P2-L1 vertical in progress – 10%
  • Grouting work for PT of P2 slab in progress – 25%
2019-03-31
  • Two Tower crane installed and working.
  • Raft foundation concrete casting completed – 100%.
  • Water tank top slab concrete casting completed – 100%
  • GF to 1st podium vertical concrete casting work is completed – 100%
  • Formwork for P1 slab is completed – 100%
  • Reinforcement work for P1 slab is completed – 90%
  • Post tension work for P1 slab in progress – 80%
  • MEP work for P1 slab in progress – 80%
  • Concrete casting for P1 slab in progress – 70%
  • Rebar work for P1-P2 slab in progress – 10%
  • Shoring beam and precast panel removing work completed -100%