Jewelz

Check More Updates
Timelapse Video
2019-06-30
  • Concrete casting of P2 slab is completed – 100%.
  • Deshuttering work of P1 slab soffit in progress – 98%
  • Grouting work for PT of P1 slab is completed – 100%
  • Reinforcement work for P2-L1 vertical is completed – 100%
  • MEP work for P2-L1 vertical is completed – 100%
  • Formwork for P2-L1 vertical is completed – 100%
  • Concrete casting work for P2-L1 vertical is completed – 100%
  • Grouting work for PT of P2 slab is completed – 100%
  • Formwork for L1 Slab is completed - 100%
  • Reinforcement work for L1 slab in progress – 98%
  • MEP work for L1 slab in progress – 98%
2019-05-30
  • Concrete casting of P2 slab is completed – 100%.
  • De shuttering work of P1 slab soffit in progress – 95%
  • Grouting work for PT of P1 slab is completed – 100%
  • Reinforcement work for P2-L1 vertical in progress – 95%
  • MEP work for P2-L1 vertical in progress – 95%
  • Formwork for P2-L1 vertical in progress – 95%
  • Concrete casting work for P2-L1 vertical in progress – 95%
  • Grouting work for PT of P2 slab is completed – 100%
  • Formwork for L1 Slab in progress – 65%
  • Reinforcement work for L1 slab in progress – 15%