Elitz-3:

  1. Structural piling works contractor has been appointed.
  2. Excavation work is in progress at site reached upto 35%.
  3. Secant pile casting started and progressed up to 50%
  4. Guide beam casting started and progressed up to 20%
  5. RTA construction NOC has been received.
  6. Shoring approval has been received from authority.
  7. Mobilization NOC has been received.
2024-01-31

Elitz-3:

  1. Structural piling works contractor has been appointed.
  2. Excavation work is in progress at site.
  3. Secant pile casting started and progressed up to 32%
  4. Guide beam casting started and progressed up to 18%
  5. RTA construction NOC has been received.
  6. Shoring approval has been received from authority.
  7. Mobilization NOC has been received.