ELZ

Check More Updates
2019-06-30
  • Fencing permit received and fencing completed.
  • Topographical survey completed.
  • Soil testing Completed.
  • ELZ sign board erected- 3 no’s- 100%
  • Shoring drawing approved and permit received.
  • Appointment of shoring contractor done. Mobilization of enabling contractor in progress.
  • Load schedule confirmation received from Master developer.
  • Traffic impact study in progress.
  • Guide beam concrete casting work in progress – 40%
  • Shoring pile casting in progress – 12%
2019-05-30
  • Fencing permit received and fencing completed.
  • Topographical survey completed.
  • Soil test work Completed.
  • ELZ sign board erected- 3 no’s- 100%
  • Shoring drawing approved and permit received.
  • Appointment of Shoring contractor done. Mobilization of enabling contractor in progress
  • Load schedule confirmation received from Master developer.
  • Traffic impact study in progress.

PROJECT LOCATION