JavaScript is off. Please enable to view full site.

Glamz

Check More Updates
Timelapse Video
2019-01-01

CIVIL WORKS:

  • Landscape area work is in progress.
  • Swimming pool’s testing works in progress.
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has been completed.
  • Tower-1: Block Work has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tiling work has been completed for all floors.
  • Tower-1: Suspension for false ceiling from 1st to 15th floor in dry area (kitchen) and corridor from 2nd to 10th floor has completed.
  • Tower-1: False ceiling closing work is in progress from 1st to 6th floor
  • Tower-1: Wall primer and stucco 1st to 15th floor is in progress.
  • Tower-1: Wet area floor tiling work has been completed for all floors.
  • Tower-1: Dry area floor tiling work has been completed for all floors.
  • Tower-1: Corridor area floor tiling 1st to 15th floor has completed
  • Tower-1: External plaster work on Elevation A, B, C, D has completed
  • Tower-1: Sliding door installation is in progress on 2nd to 13th floor.
  • Tower-1: Folding door installation is in progress on 1st to 6th floor.
  • Tower-1: External painting work on 1st to 15th floor is in progress @ Elevation A, C, E, F
  • Tower-1: Wardrobe installation is in progress on 1st to 15th floor.
  • Tower-1: Kitchen cabinet installation is in progress on 1st to 15th floor.
  • Tower-1: wooden door installation is in progress on 2nd to 6th floor.
  • Tower-1: Balcony installation is in progress on 2nd to 15th floor
  • Tower-1: Curtain wall installation is in progress on 1st to 15th floor Elevation A, C, F
  • Tower-2: Roof floor waterproofing has been completed.
  • Tower-2: Block Works has been completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tiling work has been completed for all floors.
  • Tower-2: Suspension work for false ceiling 1st to 15th (kitchen) floor has completed.
  • Tower-2: Wall primer and stucco from 1st to 15th floor is in progress.
  • Tower-2: False ceiling closing at 1st to 5th floor is in progress.
  • Tower-2: Dry area floor tiling work has been completed for all floors.
  • Tower-2: Corridor area floor tiling has been completed for all floors.
  • Tower-2: Staircase granite work has completed for all floors.
  • Tower-2: External plaster work on Elevation A, B, C, D is in progress.
  • Tower-2: Wardrobe installation is in progress on 1st to 15th floor.
  • Tower-2: Kitchen cabinet installation is in progress on 1st to 15th floor.
  • Tower-2: Balcony installation is in progress on 2nd to 14th floor.
  • Tower-2: Sliding door installation is in progress on 2nd to 12th floor.
  • Tower-2: Folding door installation is in progress on 1st to 7th floor.
  • Tower-2: Curtain wall installation is in progress on 1st to 15th floor Elevation A, B, C, D
  • Tower-2: External plaster work on Elevation A, B, C, D has completed.
  • Tower-2: External painting work on 1st to 15th floor is in progress @ Elevation A, B, C, D.

MEP Works:

  • Tower-1: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-1: Light & power wiring up to 15th floor, power cable pulling up to 15th floor, roof completed.
  • Tower-1: Drainage completed up to 14th floor, Roof also completed, risers completed, GF, Basement, P-1 completed, Podium 2 in progress.
  • Tower-1: water supply up to 15th floor, roof work completed, water pump room in progress.
  • Tower-1: FCU installation up to 15th floor.
  • Tower-1: Ducting 90% completed up to 15th floor.
  • Tower-1: Riser ducts completed 10 out of 10 up to 7th  remaining in progress & 5 riser ducts up to 15th floor.
  • Tower-1: Chilled water network up to 15th floor, Roof completed.
  • Tower-1: Firefighting network up to 15th floor, Pump room in progress & basement, podium work 95% completed, FHRC typical 30 no’s installed out of 60.
  • Tower-1: Chillers, FAHU, GRP TANK installed. CHW & FAHU piping completed.
  • Tower-1: Structural cabling work up to 15th floor.
  • Tower-1: LPG branch piping works completed up to 7th floor.
  • Tower-1: DB termination total 15 floors completed typical, GF & roof in progress, SMDB completed up to 8th floor, from 9thin progress.
  • Tower-1: Transformer delivered & LV cabling work, termination in progress.
  • Tower-1: LV room electrical GF completed 70% in progress.
  • Tower-2: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-2: Light, power wiring, power cable pulling up to 15th floor completed.
  • Tower-2: Drainage completed up to 14th, roof also completed, risers completed.
  • Tower-2: Water supply up to 15th floor, roof completed
  • Tower-2: FCU installation completed up to 15th floor.
  • Tower-2: Ducting in progress up to 15th.
  • Tower-2: Chilled water network up to 15th floor, roof completed.
  • Tower-2: Firefighting network up to 15th floor, Pump room in progress & basement, podiums works are up to 95%.
  • Tower-2: Structural cabling work up to 15th floor.
  • Tower-2: Chillers, FAHU, GRP TANK installed. CHW & FAHU piping completed.
  • Tower-2: LPG branch piping works in progress up to 6th floor.
  • Tower-2: DB termination total 15 floors completed typical, GF & roof in progress.
  • Tower-2: Transformer delivered & LV cabling work termination in progress.
  • Tower-2: LV room electrical GF completed 60% in progress.
2018-12-15

CIVIL Works:

 

  • Landscape area work is in progress.
  • Swimming pool’s testing works in progress.
  • Superstructure work is completed for both Towers.
  • Tower-1: Roof floor water proofing has been completed.
  • Tower-1: Block Work has been completed for all floors.
  • Tower-1: Internal Plastering work has been completed for all floors.
  • Tower-1: Wall Tiling work has been completed for all floors.
  • Tower-1: Suspension for false ceiling from 1s floor to 15th in dry area (kitchen) and corridor from 2nd to 10th.
  • Tower-1: False ceiling closing work from 1st to 6th floor
  • Tower-1: Wall primer and stucco 1st to 15th floor is in progress.
  • Tower-1: Wet area floor tiling work has been completed for all floors.
  • Tower-1: Dry area floor tiling work has been completed for all floors.
  • Tower-1: Corridor area floor tiling 1st to 15th floor has completed
  • Tower-1: External plaster work on Elevation A, B, C, D has completed
  • Tower-1: Sliding door installation is in progress on 2nd floor to 12th floor.
  • Tower-1: Folding door installation is in progress on 1st floor to 6th floor.
  • Tower-1: External painting work on 1st to 15th floor is in progress @ Elevation A, C, E, F
  • Tower-1: Wardrobe installation is in progress on 1st to 15th floor.
  • Tower-1: Kitchen cabinet installation is in progress on 1stto 15th floor.
  • Tower-1: wooden door installation is in progress on 2nd and 6th floor.
  • Tower-1: Balcony installation is in progress on 2nd to 15th floor
  • Tower-1: Curtain wall installation is in progress on 1st to 15th floor Elevation A, C, F
  • Tower-2: Roof floor waterproofing has been completed.
  • Tower-2: Block Works has been completed for all floors.
  • Tower-2: Internal plastering work has been completed for all floors.
  • Tower-2: Wall Tiling work has been completed for all floors.
  • Tower-2: Suspension work for false ceiling 1st to 15th (kitchen) floor has completed.
  • Tower-2: Wall primer and stucco 1stto 15th floor is in progress.
  • Tower-2: False ceiling closing at 1st to 5th floor is in progress.
  • Tower-2: Dry area floor tiling work has been completed for all floors.
  • Tower-2: Corridor area floor tiling has been completed for all floors.
  • Tower-2: Staircase granite work on 1st to 15th floor is in progress.
  • Tower-2: External plaster work on Elevation A, B, C, D is in progress.
  • Tower-2: Wardrobe installation is in progress on 1st to 14th floor.
  • Tower-2: Kitchen cabinet installation is in progress on 1stto 15th floor.
  • Tower-2: Balcony installation is in progress on 2nd to 14th floor.
  • Tower-2: Sliding door installation is in progress on 2nd floor to 12th floor.
  • Tower-2: Folding door installation is in progress on 1st floor to 7th floor.
  • Tower-2: Curtain wall installation is in progress on 1st to 15th floor Elevation A, B, C, D
  • Tower-2: External plaster work on Elevation A, B, C, D has completed.
  • Tower-2: External painting work on 1st to 15th floor is in progress @ Elevation A, B, C, D.

 

MEP Works:

 

  • Tower-1: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-1: Light & power wiring up to 15th floor, power cable pulling up to 15th floor, roof completed.
  • Tower-1: Drainage completed up to 14th floor, Roof also completed, risers completed.
  • Tower-1: water supply up to 15th floor, roof work completed.
  • Tower-1: FCU installation up to 15th floor.
  • Tower-1: Ducting 90% completed up to 15th floor.
  • Tower-1: Chilled water network up to 15th floor, Roof completed.
  • Tower-1: Firefighting network up to 15th floor, Pump room in progress & basement, podium work 95% completed
  • Tower-1: Chillers, FAHU, GRP TANK installed. CHW & FAHU piping completed.
  • Tower-1: Structural cabling work up to 15th floor.
  • Tower-1: LPG branch piping works completed up to 7th floor.
  • Tower-1: DB termination total 15 floors completed typical, GF & roof in progress
  • Tower-1: Transformer delivered & LV cabling work, termination in progress.
  • Tower-1: LV room electrical GF completed 70% in progress.
  • Tower-2: 1st fix wall conduits& plumbing PEX Pipes completed up to 15th floor.
  • Tower-2: Light, power wiring, power cable pulling up to 15th floor completed.
  • Tower-2: Drainage completed up to 14th, roof also completed, risers completed.
  • Tower-2: Water supply up to 15th floor, roof completed
  • Tower-2: FCU installation completed up to 15th floor.
  • Tower-2: Ducting in progress up to 15th.
  • Tower-2: Chilled water network up to 15th floor, roof completed.
  • Tower-2: Firefighting network up to 15th floor, Pump room in progress & basement, podiums work are up to 95%.
  • Tower-2: Structural cabling work up to 15th floor.
  • Tower-2: Chillers, FAHU, GRP TANK installed. CHW & FAHU piping completed.
  • Tower-2: LPG branch piping works in progress up to 6th floor.
  • Tower-2: DB termination total 15 floors completed typical, GF & roof in progress.
  • Tower-2: Transformer delivered & LV cabling work termination in progress.
  • Tower-2: LV room electrical GF completed 60% in progress.

WALKTHROUGH VIDEO

PROJECT LOCATION