JavaScript is off. Please enable to view full site.

Glamz

Check More Updates
Timelapse Video
2019-06-30

CIVIL WORKS:

  • Landscape area soiling work has progressed up to 75%.
  • Swimming pool’s finishing work has progressed up to 85%.
  • Entrance lobby area finishing work has progressed up to 40%.
  • Corridor False ceiling closing work has progressed up to 50%
  • Dry areas false ceiling closing work has progressed up to 60%.
  • Wall primer and stucco has progressed up to 60%.
  • Sliding door installation has progressed up to 90%.
  • Folding door installation has progressed up to 65%.
  • Wooden door installation has progressed up to 55%
  • Main door installation has progressed up to 40%.
  • Shoe rack installation has progressed up to 7th floor - 25%
  • Balcony handrail installation has progressed up to 75%
  • Curtain wall installation has progressed up to 90%
  • External Mashrabia work has progressed up to 90%
  • Tennis court and badminton court fencing has been completed.
  • Tennis court and badminton court floor base coat has been completed.

MEP Works:

  • Roof ducting work has progressed up to 30%
  • Riser ducts have has progressed up to 90%
  • 45 of 60 Fire Hose Reel Cabinets have been installed in all typical floors
  • DB termination has progressed up to 85%.
  • Panel installation and Cable Termination in LV room has progressed up to 75%.
  • Chandeliers installation has progressed up to 50%.
  • Switches & sockets has progressed up to 30%.
  • Sanitary wares Installation has progressed up to 50%.
  • Installation of Ducts has been completed all typical floors.
  • Transformers have been delivered, HV cable pulling and termination to transformer from DEWA has been completed.
2019-05-30

CIVIL WORKS: 

  • Landscape area soiling work is in progress.
  • Swimming pool’s finishing work is completed up to 80%
  • Entrance lobby area finishing work is in progress
  • Tennis court and badminton court fencing has been completed
  • Tennis court and badminton court floor base coat has been completed
  • Wall Tiling work has been completed for all floors.
  • Corridor False ceiling closing in progress up to 8th floor
  • Dry areas False ceiling closing work is in progress from 1st to 8th  floor
  • Wall primer and stucco 1st to 15th floor is in progress.
  • Wet area floor tiling work has been completed for all floors.
  • Dry area floor tiling work has been completed for all floors.
  • Corridor area floor tiling work from 1st to 15th floor has been completed
  • Sliding door installation is in progress from 1st to 14th floor.
  • Folding door installation is in progress from 1st to 11th floor.
  • External painting work from 1st to 15th  floor is in progress @ Elevation A,C,E,F
  • Wardrobe installation has been completed in all floors
  • Kitchen cabinet installation has been completed in all floors
  • Wooden door installation is in progress from 1st to 8th floors.
  • Main door installation is completed up to 5th floor and progressing well from 6th to 15th floor
  • Shoe rack installation is completed up to 7th floor
  • Balcony handrail installation is in progress from 1st  to 14th  floor
  • Curtain wall installation is in progress from 1st to 15th  floor Elevation A,C,F
  • External Mashrabia work has been completed up to 90%

 

MEP Works: 

  • 1st fix wall conduits & plumbing PEX Pipes have been completed up to 15th floor.
  • Light and power cable pulling up to roof has been completed.
  • Drainage network is completed on all typical floors and is in progress at Podium 2
  • Water supply installation has been completed up to roof floor
  • FCU installation has been completed up to 15th floor.
  • Installation of Ducts has been completed up to 95% in all typical floors
  • Riser ducts have been completed up to 85%
  • Chilled water network has been completed up to roof floor
  • Fire-fighting network has been completed in all floors
  • Fire Fighting Pump room installation works in progress at basement level
  • 30 of 60 Fire Hose Reel Cabinets have been installed in all typical floors
  • Chillers, FAHU & GRP water tanks have been installed along with their piping network
  • ELV Structural cabling works are in progress on all floors.
  • LPG branch piping works have been completed up to 7th floor.
  • DB termination in all typical floors have been completed & are in progress in Ground and Roof Floors.
  • Transformers have been delivered & LV cable termination activities are in progress.
  • Panel installation and Cable Termination in LV room has progressed up to 75%.
  • HV cable pulling and termination to transformer from DEWA has been completed.

WALKTHROUGH VIDEO

PROJECT LOCATION