2019-05-30
  • Mobilization permit for fencing obtained.
  • Demarcation completed.
  • Signboards installation completed.
  • Hoarding works & site set up works completed.
  • Enabling works contractor appointed and work permits in progress.
  • Enabling contractor site mobilization works in progress.
  • Excavation works in progress.
  • Drilling works for shoring in progress and I-beam Material delivered to site 
  • Guide wall preparation work in progress 
  • Casting platform for Pre-cast panels in progress.
2019-04-30
  • Mobilisation of the site including workers welfare and Engineers offices to obtain Zero level inspection and COC.
  • Demarcation completed.
  • Two drilling machines getting assembled for drilling works & mobile crane for lifting purpose.
  • Sign boards installation completed.
  • JCB and bobcat working for site access levelling and formation.
  • Hoarding works completed.
  • Awaiting reinforcement delivery to initiate fabrication works for the shoring precast panels.
  • Enabling works Contractor appointed and work permits in progress.
  • Enabling Contractor site mobilization works in progress.
  • Shoring I beam has been delivered to site 30 %.
  • RTA Stage 1 Approved awaiting approval from Road Traffic Authority