Timelapse Video

Progress ( 31-July-2019 )

excavation
12%
shoring
59.25%
concrete
52.32%
blockwork
0%
internal plaster
0%
external plaster
0%
internal paint
0%
external paint
0%
tiling marble
0%
mechanical
0%
electrical
0%
plumbing
0%
hvac
0%
handrail fencing
0%
false ceiling
0%
glass aluminium
0%
wooden doors
0%
wardrobe
0%
kitchen
0%
lighting
0%
bath sanitary
0%
2019-06-30
  • Mobilization permit for fencing obtained.
  • Demarcation completed.
  • Sign boards installation completed.
  • Hoarding works and site set up works completed.
  • Enabling works contractor appointed and work permits in progress.
  • Enabling contractor site mobilization works in progress.
  • Excavation works in progress at 40%
  • I-beam shoring works 100% completed
  • Guide wall preparation works in progress at 60%
  • Concrete Shoring Piles 30% completed