Miraclz

Check More Updates
Timelapse Video

Progress ( 31-July-2019 )

excavation
100%
shoring
100%
concrete
59.88%
blockwork
39%
internal plaster
29%
external plaster
0%
internal paint
2%
external paint
0%
tiling marble
0%
mechanical
9%
electrical
11%
plumbing
9%
hvac
6%
handrail fencing
0%
false ceiling
0%
glass aluminium
0%
wooden doors
0%
wardrobe
0%
kitchen
0%
lighting
0%
bath sanitary
0%
2019-06-30

Substructure:  

  • Substructure works completed- 100%

Floor Slab:

  • 15th Floor slab casting completion – 100%
  • 15th to 16th floor columns casting completion - 100%
  • 16th floor slab shuttering works in progress – 90%
  • 16th floor slab reinforcement works in progress – 90%
  • 16th floor slab casting completed – 50%    

Core Wall:

  • Core wall casting completed F17-F18 level – 100%
  • Core wall reinforcement in progress F18-F19 level – 80%
  • Core wall shuttering in progress F18 - F19 level – 50%

 

Internal Finishes:   

Blockwork :

  • 1st floor blockwork Completion - 100%
  • 2nd floor blockwork Completion - 100%
  • 3rd floor blockwork Completion -  100% 
  • 4th floor blockwork Completion -  98%
  • 5th floor block work Completion – 98%
  • 6th floor block work Completion – 98% 
  • 7th floor block work Completion – 95% 
  • 8th floor block work Completion – 90% 
  • 9th floor block work Completion – 90% 
  • 10th floor block work Completion – 55% 
  • 11th floor block work Completion – 15% 

Plastering :

  • 1st floor plastering Completion  - 95%
  • 2nd floor plastering Completion  - 95%
  • 3rd floor plastering Completion  -  95% 
  • 4th   floor plastering Completion -  90%
  • 5th   floor plastering Completion -  80%
  • 6th   floor plastering Completion - 80%
  • 7th   floor plastering Completion -  80%
  • 8th   floor plastering Completion -  45%
  • 9th   floor plastering Completion -  35%
  • 10th floor plastering completion – 20%

Painting :

  • 1st  floor painting Completion  - 40%
  • 2nd floor painting Completion  - 40%
  • 3rd  floor painting Completion  -  30% 
  • 4th   floor painting Completion -  30%
  • 5th   floor painting Completion -  20%

MEP:  High level MEP works in progress

  • Basement - 52%
  • Ground floor - 40%
  • P1 level – 40%
  • P2 level – 40%
  • 1st floor – 60%
  • 2nd floor – 60%
  • 3rd floor  - 45%
  • 4th floor – 30%
  • 5th floor – 30%
  • 6th floor – 25%
  • 7th floor – 20%
  • 8th floor – 20%
  • 9th floor – 15%
  • 10th floor – 10%
  • 11th floor – 10%