Miraclz

Check More Updates
Timelapse Video
2019-04-30

Substructure:

 

  • Substructure works completed- 100%

 

Floor Slab:

 

  • 11th Floor slab casting completion – 100%
  • 11th to 12thfloor columns casting completion - 50%
  • 12th floor slab shuttering works in progress – 30%

 

Core Wall:

 

  • Core wall casting completed F13-F14 level – 100%
  • Core wall reinforcement in progress F14-F15 level – 20%
  • Core wall shuttering InProgress F14-F15 level  – 20%

 

Internal Finishes:

 

Block Works:

 

  • 1st  floor blockwork Completion  - 85%
  • 2nd floor blockwork Completion  - 95%
  • 3rd  floor blockwork Completion  -  90%  
  • 4th   floor blockwork Completion -  85% 
  • 5th floor block work Completion – 70%
  • 6th floor block work Completion – 60%  
  • 7th floor block work Completion – 30%  

 

Plastering:

 

  • 1st  floor plastering Completion  - 50%
  • 2nd floor plastering Completion  - 35%
  • 3rd  floor plastering Completion  -  20%  
  • 4th   floor plastering Completion -  10% 

 

MEP Works:

 

  • High level MEP works in progress
    • Basement - 45% 
    • Ground floor - 35%
    • P1 level – 30%
    • P2 level – 30%
    • 1st floor – 25%
    • 2nd floor – 30%
    • 3rd floor  - 20%
    • 4th floor – 15%
    • 5th floor – 15%
    • 6th floor – 10%
2019-03-31

Substructure: 

 

  • Substructure works completed- 100%

 

Floor Slab: 

 

  • Roof of podium slab casting completion – 100% 
  • 8th Floor slab casting completion – 100%
  • 8th to 9th floor columns casting completion -  85%
  • 9th floor slab shuttering works in progress – 80%
  • 9th floor slab reinforcement works in progress – 70%
  • 9th floor slab Casting completion – 50%

 

Core Wall: 

 

  • Core wall casting completed F10-F11 level – 100%
  • Core wall reinforcement in progress F11-F12 level – 40%
  • Core wall shuttering in progress F11-F12 level – 20%

 

Internal Finishes:

 

  • 1st floor blockwork Completion - 70%
  • 2nd floor blockwork Completion - 85%
  • 3rd floor blockwork Completion - 60%  
  • 4th floor blockwork Completion - 35% 
  • 5th floor block work Completion – 10%

 

MEP:

  • High level MEP works in progress for basement – 25%
  • High level MEP works in progress for ground floor - 15%