Miraclz

Check More Updates
Timelapse Video
2019-03-15

 Substructure: 

 

  • Substructure works completed- 100%

 

Floor Slab: 

 

  • Podium roof slab casting completion – 100% 
  • 7th floor slab casting completion – 100%
  • 7th to 8th floor columns casting completion - 100%
  • 8th floor slab shuttering works in progress – 100%
  • 8th floor slab reinforcement works in progress – 90%
  • 8th floor slab Casting completion – 50%

 

Core Wall: 

 

  • Core wall casting completed F9-F10 level – 100%
  • Core wall reinforcement in progress F10-F11 level – 30%
  • Core wall shuttering in progress F10-F11 level – 20%

 

Internal Finishes:

 

  • 2nd floor blockwork in progress  - 75% completed   
  • 3rd  floor blockwork in progress  -  30% completed   
  • 4th   floor blockwork in progress  -  15% completed   

 

MEP:

  • High level MEP works in progress for basement and ground floor.
2019-03-01

Substructure: 

 

  • Substructure works completed- 100%

 

Floor Slab: 

  • Podium 2 floor slab casting completion – 100%
  • roof of podium slab casting completion – 82% 
  • 7th floor slab casting completion – 100%
  • 7th to 8th floor columns casting completion - 75%
  • 8th floor slab shuttering works in progress – 50%
  • 8th floor slab reinforcement works in progress – 40%

 

Core Wall: 

 

  • Core wall casting completed F8-F9 level – 100%
  • Core wall reinforcement and shuttering in progress F9-F10 level – 100%
  • Core wall shuttering completed F9-F10 level – 80%

 

Internal Finishes:

 

  • 2nd floor blockwork in progress - 35% completed   

 

MEP:

  • High level MEP works in progress for basement.