Timelapse Video

Progress ( 30-Sep-2019 )

excavation
100%
shoring
100%
concrete
67.49%
blockwork
53%
internal plaster
45%
external plaster
0%
internal paint
14%
external paint
0%
tiling marble
1.25%
mechanical
15%
electrical
14%
plumbing
14%
hvac
12%
handrail fencing
0%
false ceiling
0%
glass aluminium
0%
wooden doors
0%
wardrobe
0%
kitchen
0%
lighting
0%
bath sanitary
1%