Progress ( 31-Mar-2020 )

excavation
100%
shoring
100%
concrete
97.5%
blockwork
85%
internal plaster
75%
external plaster
55%
internal paint
37%
external paint
0%
tiling marble
45.48%
mechanical
41%
electrical
40%
plumbing
39%
hvac
40%
handrail fencing
0%
false ceiling
39%
glass aluminium
48.31%
wooden doors
0%
wardrobe
7.25%
kitchen
7.09%
lighting
0%
bath sanitary
2%