PROGRESS ( 28-Feb-2023 )

Excavation
100%
Shoring
100%
Concrete
95.94%
Blockwork
56.96%
Internal Plaster
15%
Electrical
37%
Hvac
0%
Glass Aluminium
0%
Wooden doors
0%
Wardrobe
0%
Kitchen
0%
Plumbing
0%
External Plaster
0%
Internal Paint
5%
External Paint
0%
Tiling Marble
0%
Mechanical
20%
Handrail Fencing
0%
False ceiling
0%
Lighting
0%
Bath sanitary
0%