2023-11-01

PROGRESS ( 15-Nov-2023 )

Excavation
100%
Shoring
100%
Concrete
99.5%
Blockwork
99%
Internal Plaster
98%
Electrical
75%
Hvac
68%
Glass Aluminium
80%
Wooden doors
0%
Wardrobe
15%
Kitchen
15%
Plumbing
75%
External Plaster
98%
Internal Paint
52%
External Paint
55%
Tiling Marble
75%
Mechanical
68%
Handrail Fencing
58%
False ceiling
50%
Lighting
2%
Bath sanitary
3.72%