PROGRESS ( 15-Sep-2023 )

Excavation
100%
Shoring
100%
Concrete
100%
Blockwork
100%
Internal Plaster
100%
Electrical
99%
Hvac
98%
Glass Aluminium
100%
Wooden doors
100%
Wardrobe
100%
Kitchen
100%
Plumbing
97%
External Plaster
100%
Internal Paint
99.5%
External Paint
98%
Tiling Marble
100%
Mechanical
97%
Handrail Fencing
100%
False ceiling
100%
Lighting
100%
Bath sanitary
100%