Progress ( 30-Sep-2019 )

excavation
100%
shoring
100%
concrete
100%
blockwork
100%
internal plaster
100%
external plaster
100%
internal paint
85%
external paint
99%
tiling marble
99%
mechanical
96%
electrical
96%
plumbing
96%
hvac
96%
handrail fencing
95%
false ceiling
96%
glass aluminium
96%
wooden doors
90%
wardrobe
99.38%
kitchen
92%
lighting
60%
bath sanitary
45%