Resortz

Check More Updates
Timelapse Video
2019-04-30

Finishing Works: 

 

  • Block work:
    • Ground floor- 100%
    • First floor- 100%
    • Second floor- 100%
    • Third floor- 100%
    • Fourth floor-100%

 

  • Plaster:
    • Ground floor-99%
    • First floor- 99.5%
    • Second floor-99.5%
    • Third floor- 99.5%
    • Fourth floor-99.5%
    • Roof- 98% 

 

  • Tiling:
    • Ground floor- 93%
    • First floor- 98%
    • Second floor -98%
    • Third floor - 98%
    • Fourth floor-  98%

 

  • Paint:
    • Basement - 90% 
    • Ground floor-60%
    • First floor- 60%
    • Second floor – 55%
    • Third floor – 55%
    • Fourth floor – 45%

 

  • Joinery Work:

 

o    Wardrobe installation completion - 50%

o    Kitchen cabinet installation completion – 35%

o    Folding door installation completion – 90%

o    Sliding door installation completion – 65%

 

MEP works:

 

  • Basement       –   over all work completion – 85%
  • Ground floor   –   over all work completion - 95%
  • First floor        – overall work completion - 95%
  • Second floor   – overall work completion - 95%
  • Third floor     – overall work completion - 90%
  • Fourth floor   - overall work completion- 90%
2019-03-31

Finishing Works: 

 

  • Block work:
    • Ground floor- 99%
    • First floor- 99%
    • Second floor- 99%
    • Third floor- 99%
    • Fourth floor-99%

 

  • Plaster:
    • Ground floor-98%
    • First floor- 98%
    • Second floor-98%
    • Third floor- 98%
    • Fourth floor-97%
    • Roof- 98% 

 

  • Tiling:
    • Ground floor- 75%
    • First floor- 94%
    • Second floor -94%
    • Third floor - 93%
    • Fourth floor-  92%

 

  • Paint:
    • Basement - 90% 
    • Ground floor-40%
    • First floor- 45%
    • Second floor – 45%
    • Third floor – 35%
    • Fourth floor – 35%

 

  • Joinery Work:
    • Wardrobe installation completion - 30%
    • Kitchen cabinet installation completion – 15%
    • Folding door installation completion – 60%
    • Sliding door installation completion – 26%

 

 

MEP works:

 

  • Basement       –   over all work completion – 85%
  • Ground floor   –   over all work completion - 90%
  • First floor        – overall work completion - 90%
  • Second floor   – overall work completion - 90%
  • Third floor     – overall work completion - 75%
  • Fourth floor   - overall work completion- 65%