JavaScript is off. Please enable to view full site.

Resortz

Check More Updates
Timelapse Video

Progress ( 31-July-2019 )

excavation
100%
shoring
100%
concrete
100%
blockwork
100%
internal plaster
100%
external plaster
100%
internal paint
75%
external paint
95%
tiling marble
90%
mechanical
95%
electrical
95%
plumbing
95%
hvac
95%
handrail fencing
70%
false ceiling
95%
glass aluminium
95%
wooden doors
61.48%
wardrobe
99.38%
kitchen
92%
lighting
0%
bath sanitary
30%
2019-06-30

Finishing Works:  

  • Tiling:
    • Ground floor- 97%
    • First floor- 99%
    • Second floor -99%
    • Third floor – 99%
    • Fourth floor- 98.5%
  • Paint:
    • Basement - 94%
    • Ground floor-90%
    • First floor- 90%
    • Second floor – 90%
    • Third floor – 90%
    • Fourth floor – 90%
    • External paint- 45%
  • Joinery works:
    • Wardrobe installation completion - 90%
    • Kitchen cabinet installation completion – 85%
    • Folding door installation completion – 100%
    • Sliding door installation completion – 98%

MEP Works:

  • Basement           – over all work completion – 95%
  • Ground floor     – over all work completion - 98%
  • First floor            – overall work completion – 98%
  • Second floor      – overall work completion - 98%
  • Third floor          – overall work completion - 98%
  • Fourth floor       - overall work completion- 98%
  • Roof                      – over all work completion – 95%

General works:

  • Swimming pool tiling completed 95%
  • Land scape planting in progress
  • Staircase handrail installation in progress
  • Lift installation - 98% completed
  • Curtain wall for panaromic lift completed
  • Parking flooring 85% completed
  • Entrance lobbies- 80% completed

WALKTHROUGH VIDEO

PROJECT LOCATION