Resortz

Check More Updates
Timelapse Video
2019-06-30

Finishing Works:  

  • Tiling:
    • Ground floor- 97%
    • First floor- 99%
    • Second floor -99%
    • Third floor – 99%
    • Fourth floor- 98.5%
  • Paint:
    • Basement - 94%
    • Ground floor-90%
    • First floor- 90%
    • Second floor – 90%
    • Third floor – 90%
    • Fourth floor – 90%
    • External paint- 45%
  • Joinery works:
    • Wardrobe installation completion - 90%
    • Kitchen cabinet installation completion – 85%
    • Folding door installation completion – 100%
    • Sliding door installation completion – 98%

MEP Works:

  • Basement           – over all work completion – 95%
  • Ground floor     – over all work completion - 98%
  • First floor            – overall work completion – 98%
  • Second floor      – overall work completion - 98%
  • Third floor          – overall work completion - 98%
  • Fourth floor       - overall work completion- 98%
  • Roof                      – over all work completion – 95%

General works:

  • Swimming pool tiling completed 95%
  • Land scape planting in progress
  • Staircase handrail installation in progress
  • Lift installation - 98% completed
  • Curtain wall for panaromic lift completed
  • Parking flooring 85% completed
  • Entrance lobbies- 80% completed
2019-05-30

Finishing Works:  

  • Tiling:

o   Ground floor- 96%

o   First floor- 99%

o   Second floor -99%

o   Third floor – 99%

o   Fourth floor-  98.5%  

  • Paint:

o   Basement - 92%

o   Ground floor-80%

o   First floor- 80%

o   Second floor – 80%

o   Third floor – 75%

o   Fourth floor – 65%

o    External paint- 30% 

  • Joinery Work:

o    Wardrobe installation completion - 66%

o    Kitchen cabinet installation completion  – 51%

o    Folding door installation completion – 95%

o    Sliding door installation completion – 85%%

 

MEP works: 

  • Basement       –   over all work completion – 90%
  • Ground floor   –   over all work completion - 98%
  • First floor        – overall work completion – 97.5%
  • Second floor   – overall work completion - 97%
  • Third floor     – overall work completion - 94%
  • Fourth floor   - overall work completion- 94%
  • Roof – over all work completion – 85%

 

General Works: 

  • Swimming pool tiling in progress
  • Land scape planting in progress
  • Stair case hand rail installation in progress
  • Lift installation 95% completed
  • Curtain wall for panaromic lift completed
  • Parking flooring 75% completed
  • Entrance lobbies- 75% completed