2023-11-01

PROGRESS ( 15-Nov-2023 )

Excavation
100%
Shoring
100%
Concrete
37.11%
Blockwork
2.73%
Internal Plaster
7.15%
Electrical
0%
Hvac
0%
Glass Aluminium
0%
Wooden doors
0%
Wardrobe
0%
Kitchen
0%
Plumbing
0%
External Plaster
0%
Internal Paint
0%
External Paint
0%
Tiling Marble
0%
Mechanical
0%
Handrail Fencing
0%
False ceiling
0%
Lighting
0%
Bath sanitary
0%