Starz

Check More Updates
Timelapse Video
2019-03-15

CIVIL Works:

  • Water Supply Authority Inspection from DEWA has been approved.
  • Breeching Inlet DCD inspection has been approved.
  • Electricity from DEWA authority inspection is under progress.
  • Landscaping activities have progressed up to 95%.
  • Planting for Date Palm Trees have been completed.
  • Swimming pool’s finishing works have progressed up to 95%.
  • Swimming Pool’s Deck Area Tiling works are completed up to 90%.
  • Tennis court and badminton court fencing has been completed.
  • Gym and Multipurpose hall area finishing work is in progress.
  • Jogging track area heel kerbs has been completed for both towers.
  • Entrance lobby finishing work is in progress up to 60%.
  • Installation of Monorail for Window Cleaning System is under progress.
  • Superstructure work has been executed for both Towers.
  • Tower-1: Water proofing in Roof Floor is completed.
  • Tower-1: Block work installation has been completed in all floors.
  • Tower-1: Internal Plastering work has been completed in all floors.
  • Tower-1: Wall Tile work has been completed in all floors.
  • Tower-1: Grid-work and Suspension for False Ceiling has been executed from floors 1st to 15th.
  • Tower-1: Gypsum board installation for false ceiling in all apartments has been executed till the 15th floor
  • Tower-1: Wall primer and stucco works have been completed in all typical floors
  • Tower-1: Floor tiling works for wet areas in all floors have been completed.
  • Tower-1: Tile installation for Dry areas have been completed in all floors.
  • Tower-1: Tile installation for Corridor areas have been completed in all floors.
  • Tower-1: Corridor area false ceiling suspension has been completed for all floors.
  • Tower-1: Closure for False Ceiling in Corridor area is completed in all typical floors.
  • Tower-1: Sliding door installation has been completed for all floors.
  • Tower-1: Folding door installation has been completed for all floors.
  • Tower-1: Kitchen cabinet installation has been completed for all floors.
  • Tower-1: Wardrobe installation has been completed from 1st to 15th  floors.
  • Tower-1: Wooden door installation is completed on all typical floors
  • Tower-1: Mashrabia installation work has been completed in all elevations
  • Tower-1: External plastering work has been completed.
  • Tower-1: External painting work on 1st to 15th floor has been completed in Elevation A, B, C, D.
  • Tower-1: Curtain wall installation work is completed from 2nd  to 13th floor and is in progress on the 14th and 15th floor at Elevation A, B, C, D.
  • Tower-2: Water proofing in Roof Floor is completed.
  • Tower-2: Block Work and plastering activities in all floors has been completed.
  • Tower-2: Wall Tile work has been completed for all floors.
  • Tower-2: False ceiling suspension work from 1st to 15th floor has completed.
  • Tower-2: wet area floor tiling work has been completed for all floors.
  • Tower-2: In wet areas like kitchen, false ceiling closing work has been completed on all floors
  • Tower-2: Dry area Tiling work has been completed for all floors.
  • Tower-2: Corridor area floor tiling work has been completed for all floors.
  • Tower-2: Wall painting from 1st to 15th floor is in progress.
  • Tower-2: Staircase flooring has been completed for all floors.
  • Tower-2: Ceiling plaster for dry areas from 10th to 15th floor is completed.
  • Tower-2: Ceiling plaster for balcony from 1st to 15th floor is in progress.
  • Tower-2: Folding door installation is completed on all typical floors.
  • Tower-2: Wooden door installation is in progress from 2nd to 14th floor.
  • Tower-2: Balcony handrail installation is completed from 2nd to 15th floor.
  • Tower-2: Sliding door installation is completed for all floors.
  • Tower-2: Corridor area false ceiling closing work is completed for all floors.
  • Tower-2: Wardrobe installation has been completed on all floors.
  • Tower-2: Kitchen cabinet installation has been completed on all floors.
  • Tower-2: Internal painting work in progress from 2nd to 4th Floors.
  • Tower-2: External plastering work has been completed.
  • Tower-2: External painting work from 1st to 15th floor is completed in all elevations
  • Tower-2: Curtain wall installation work is completed from 2nd to 13th floor and is in progress on 14th and 15th floor.

 

MEP Works:

  • Tower-1: 1st fix wall conduits & plumbing PEX Pipes has been completed up to 15th floor.
  • Tower-1: Light and power cable pulling up to roof has been completed.
  • Tower-1: Water supply piping installation up to roof has been completed.
  • Tower-1: Network for drainage piping has been executed in all floors.
  • Tower-1: Installation of Fan Coil Unit has been completed in all floors.
  • Tower-1: Installation of Ducts have been completed till the 15th floor & is under progress at 95% on Roof floor.
  • Tower-1: Chilled water network has been completed till roof floor
  • Tower-1: Fire-fighting network has been completed in all floors & has progressed till 95% on roof
  • Tower -1: Structural cabling has been completed till the 15th floor & is under progress in the Main telephone Room.
  • Tower-1: Chillers, FAHU & GRP water tank has been installed along with its piping network on Roof
  • Tower-1: Fire alarm accessories has been completed in all apartments up to 15th floor.
  • Tower 1: Installation of accessories for Fire Alarm System is under progress in all corridor areas.
  • Tower 1: Installation of switch socket accessories has been completed on all floors
  • Tower-1: Piping network for LPG is completed till the 11th floor and is under progress at 75% on the Roof floor.
  • Tower 1: Sanitary wares installation has been completed till 50%
  • Tower-1: Electrical Panel’s installation work in LV room has been completed.
  • Tower 1: HVAC grilles and diffusers fire alarm accessories has be completed till 7th floor
  • Tower-1: DB termination is completed on all floors.
  • Tower-1: Balcony Light fitting installation is under progress in Elevation A.
  • Tower-1: Light Fittings installation is under progress on 1st and 2nd floors.
  • Tower-1: Transformers have been delivered & its cable termination with LV panel has been completed
  • Tower-1: Breeching inlet cabinet has been installed in Ground floor.
  • Tower-1: Fire alarm Cabinet’s commissioning in Management room is under progress.
  • Tower 1: HV cable pulling and termination to transformer from DEWA has been completed
  • Tower-2: 1st fix wall conduits & plumbing PEX Pipes have been completed up to 15th floor.
  • Tower-2: Light and power cable pulling up to roof has been completed.
  • Tower 2: Sanitary wares installation has been completed till 80%
  • Tower-2: Light Fittings installation is under progress on the 4th floor.
  • Tower-2: Water supply piping installation up to roof has been completed.
  • Tower-2: Network for drainage piping has been executed in all floors.
  • Tower-2: Installation of Fan Coil Unit has been completed in all floors.
  • Tower-2: Installation of Ducts has been completed till the 15th floor & is under progress up to 95% in Roof floor.
  • Tower 2: HVAC grilles and diffusers fire alarm accessories has be completed till 9th floor
  • Tower-2: Chilled water network has been completed till roof floor
  • Tower-2:  Fire-fighting network has been completed in all floors & has progressed to 95% on roof
  • Tower-2:  Structural cabling has been completed till the 15th floor & is under progress in the Main telephone Room.
  • Tower-2: Chillers, FAHU & GRP water tank has been installed along with its piping network
  • Tower-2: Fire alarm accessories has been completed in all apartments up to 15th floor.
  • Tower-2: Installation of accessories for Fire Alarm System is under progress in all corridor areas.
  • Tower-2: Installation of switch socket accessories has been completed on all typical floors
  • Tower-2: Piping network for LPG is completed till the 11th floor and is under progress at 75% on the Roof floor.
  • Tower-2: Electrical LV room works completed.
  • Tower-2: DB termination is completed on all floors.
  • Tower-2: Balcony Light fitting installation is under progress in Elevation A.
  • Tower-2: Transformers have been delivered & LV cable termination has been completed.
  • Tower-2: Breeching inlet cabinet has been installed in Ground floor.
  • Tower-2: Fire alarm Cabinet’s commissioning in Management room is under progress.
  • Tower 2: HV cable pulling and termination to transformer from DEWA has been completed
2019-03-01

CIVIL Works:

  • Landscaping activities have progressed up to 95%.
  • Planting for Date Palm Trees have been completed.
  • Swimming pool’s finishing works have progressed up to 95%.
  • Swimming Pool’s Deck Area Tiling works are completed up to 90%
  • Tennis court and badminton court fencing has been completed.
  • Gym and Multipurpose hall area finishing work is in progress well.
  • Jogging track area heel kerbs has been completed for both towers.
  • Entrance lobby finishing work is in progress up to 40%.
  • Installation of Monorail for Window Cleaning System is under progress.
  • Superstructure work has been executed for both Towers.
  • Tower-1: Water proofing in Roof Floor is completed.
  • Tower-1: Block work installation has been completed in all floors.
  • Tower-1: Internal Plastering work has been completed in all floors.
  • Tower-1: Wall Tile work has been completed in all floors.
  • Tower-1: Grid-work and Suspension for False Ceiling has been executed from floors 1st to 15th.
  • Tower-1: Gypsum board installation for false ceiling in all apartments has been executed till the 15th floor.
  • Tower-1: Wall primer, stucco works have commenced and are in progress from 1st to 15th floors.
  • Tower-1: Floor tiling works for wet areas in all floors have been completed.
  • Tower-1: Tile installation for Dry areas have been completed in all floors.
  • Tower-1: Tile installation for Corridor areas have been completed in all floors.
  • Tower-1: Corridor area false ceiling suspension has been completed for all floors.
  • Tower-1: Closure for False Ceiling in Corridor area is in progress on all typical floors.
  • Tower-1: Sliding door installation has completed for all floors.
  • Tower-1: Folding door installation has completed for all floors.
  • Tower-1: Kitchen cabinet installation has completed for all floors.
  • Tower-1: Wardrobe installation has been completed from 1st to 15th   
  • Tower-1: Wooden door installation is completed till 12th floor and is in progress on 13th to 15th floor.
  • Tower-1: Mashrabia installation work is completed in Elevation D and is in progress @ Elevation A and B.
  • Tower-1: External plastering work has been completed.
  • Tower-1: External painting work on 1st to 15th floor has been completed in Elevation A, B, C, D.
  • Tower-1: Curtain wall installation work is completed from 2nd to 13th floor and is in progress on the 14th and 15th floor at Elevation A, B, C, D.
  • Tower-2: Water proofing in Roof Floor is completed.
  • Tower-2: Block Work and plastering activities in all floors has been completed.
  • Tower-2: Wall Tile work has been completed for all floors.
  • Tower-2: False ceiling suspension work from 1st to 15th floor has completed.
  • Tower-2: wet area floor tiling work has been completed for all floors.
  • Tower-2: In wet areas like kitchen, false ceiling closing work has been completed on all floors.
  • Tower-2: Dry area Tiling work has been completed for all floors.
  • Tower-2: Corridor area floor tiling work has been completed for all floors.
  • Tower-2: Wall painting from 1st to 15th floor is in progress.
  • Tower-2: Staircase flooring has been completed for all floors.
  • Tower-2: Ceiling plaster for dry areas from 10th to 15th floor is completed.
  • Tower-2: Ceiling plaster for balcony from 1st to 15th floor is in progress.
  • Tower-2: Folding door installation is completed from 1st to 15th floor.
  • Tower-2: Wooden door installation is in progress from 2nd to 14th floor.
  • Tower-2: Balcony handrail installation is completed from 2nd to 15th floor.
  • Tower-2: Sliding door installation has completed for all floors.
  • Tower-2: Corridor area false ceiling closing work has completed for all floors.
  • Tower-2: Wardrobe installation has been completed on all floors.
  • Tower-2: Kitchen cabinet installation has been completed on all floors.
  • Tower-2: Internal painting work in progress from 2nd to 4th Floors.
  • Tower-2: External plastering work has been completed.
  • Tower-2: External painting work from 1st to 15th floor is completed @ Elevation A, B, C, D.
  • Tower-2: Curtain wall installation work is completed from 2nd to 13th floor and is in progress on 14th and 15th floor.

 

MEP Works:

  • Tower-1: 1st fix wall conduits & plumbing PEX Pipes has been completed up to 15th floor.
  • Tower-1: Light and power cable pulling up to roof has been completed.
  • Tower-1: Water supply piping installation up to roof has been completed.
  • Tower-1: Network for drainage piping has been executed in all floors.
  • Tower-1: Installation of Fan Coil Unit has been completed in all floors.
  • Tower-1: Installation of Ducts have been completed till the 15th floor & is under progress up to 95% in Roof floor.
  • Tower-1: Chilled water network has been completed till roof floor.
  • Tower-1: Fire-fighting network has been completed in all floors & has progressed till 90% on roof.
  • Tower -1: Structural cabling has been completed till the 15th floor & is under progress in the Main telephone Room.
  • Tower-1: Chillers, FAHU & GRP water tank has been installed along with its piping network on Roof.
  • Tower-1: Fire alarm accessories has been completed in all apartments up to 15th floor.
  • Tower 1: Installation of accessories for Fire Alarm System is under progress in all corridor areas.
  • Tower 1: Installation of switch socket accessories is under progress from 1st to 3rd floors.
  • Tower-1: Piping network for LPG is completed till the 11th floor and is under progress at 75% on the Roof floor.
  • Tower-1: Electrical Panel’s installation work in LV room has been completed.
  • Tower-1: DB termination is completed on all floors.
  • Tower-1: Balcony Light fitting installation is under progress in Elevation A.
  • Tower-1: Transformers have been delivered & its cable termination with LV panel is under progress.
  • Tower-1: Breeching inlet cabinet has been installed in Ground floor.
  • Tower-1: Fire alarm Cabinet’s cable terminat­ion in Management room is under progress.
  • Tower 1: HV cable pulling and termination to transformer from DEWA has been completed.
  • Tower-2: 1st fix wall conduits & plumbing PEX Pipes have been completed up to 15th floor.
  • Tower-2: Light and power cable pulling up to roof has been completed.
  • Tower-2: Water supply piping installation up to roof has been completed.
  • Tower-2: Network for drainage piping has been executed in all floors.
  • Tower-2: Installation of Fan Coil Unit has been completed in all floors.
  • Tower-2: Installation of Ducts has been completed till the 15th floor & is under progress up to 95% in Roof floor.
  • Tower-2: Chilled water network has been completed till roof floor.
  • Tower-2:  Fire-fighting network has been completed in all floors & has progressed to 90% on roof.
  • Tower-2:  Structural cabling has been completed till the 15th floor & is under progress in the Main telephone Room.
  • Tower-2: Chillers, FAHU & GRP water tank has been installed along with its piping network.
  • Tower-2: Fire alarm accessories has been completed in all apartments up to 15th floor.
  • Tower-2: Installation of accessories for Fire Alarm System is under progress in all corridor areas.
  • Tower-2: Installation of switch socket accessories is in progress on 1st floor.
  • Tower-2: Piping network for LPG is completed till the 11th floor and is under progress at 75% on the Roof floor.
  • Tower-2: Electrical LV room works completed.
  • Tower-2: DB termination is completed on all floors.
  • Tower-2: Balcony Light fitting installation is under progress in Elevation A.
  • Tower-2: Transformers delivered & LV cabling termination is under progress.
  • Tower-2: Breeching inlet cabinet has been installed in Ground floor.
  • Tower-2: Fire alarm Cabinet’s cable termination in Management room is under progress at 85%.
  • Tower 2: HV cable pulling and termination to transformer from DEWA has been completed.

WALKTHROUGH VIDEO