2023-08-31
Viewz-01

  •     Project Signboard Installation completed.-100%
  •     Appointment of shoring Contractor – completed- M/s Geo foundation.
  •     Shoring design approved from DM.
  •     TIS application under review by RTA – Awaiting DMCC approval as per RTA recommendation (9 recommendations submitted)
  •     All other Construction and Design NOC’S are in progress.
  •     RTA NOC’S must be obtained before the site work commence. Awaiting TIS approval.
  •     Site mobilization in progress and site works will be commenced immediately after the TIS/RTA NOC’S

 
Viewz 02:

  •     Fencing Work Completed- 100%
  •     Project Signboard Installation completed.-100%
  •     Appointment of shoring Contractor – completed- M/s ATLAS foundation.
  •     Shoring design approved from DM.
  •     TIS approval awaited from RTA
  •     All other Construction and Design NOC’S are in progress.
  •     RTA NOC’S must be obtained before the site work commence.
  •     Site works will be commenced immediately after the TIS/RTA NOC’S
  •     Site office and equipment mobilisation in progress.
2023-07-31
 Viewz-01

  •    Fencing Work Completed- 100%
  •    Project Signboard Installation completed.-100%
  •    Appointment of shoring Contractor – completed- M/s Geo foundation.
  •    Shoring design approved from DM.
  •    6.no.of TIS options were submitted to DMCC approval and awaiting response.
  •    All other Construction and Design NOC’S are in progress.
  •    RTA NOC’S must be obtained before the site work commence.
  •    Site mobilization will be commenced immediately after the TIS/RTA NOCs

Viewz-02

  •    Fencing Work Completed- 100%
  •    Project Signboard Installation completed.-100%
  •    Appointment of shoring Contractor – completed- M/s ATLAS foundation.
  •    Shoring design approved from DM.
  •    TIS option APPROVED by DMCC and awaiting response from RTA
  •    All other Construction and Design NOC’S are in progress.
  •    RTA NOC’S must be obtained before the site work commence.
  •    Site mobilization will be commenced immediately after the TIS/RTA NOC’S