Danube Properties Danube Properties 8005757 info@danubeproperties.ae

VIEWZ By Danube

CONSTRUCTION UPDATES

Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
Construction Updates
CHECK MORE UPDATES
2024-02-15

Viewz-01

  1. Fencing Work Completed- 100%
  2. Project Signboard Installation completed.-100%
  3. Appointment of shoring Contractor - Completed and Changed from M/s Geo foundation to M/s Atlas Foundation.
  4. Enabling subcontractor started mobilisation.
  5. Shoring Guide wall casting is in progress.
  6. Dewatering system submission is in progress.
  7. All Engineering submissions are in progress.

Viewz-02

  1. Shoring Guide-wall works 100% completed.
  2. Shoring works 100% completed.
  3. Excavation works of Enabling contractor is in progress.
  4. Building permit obtained under the name of Main Contractor (M/s Prestige)
  5. Main pile design submitted and under review by DM.
  6. Dewatering system submission is in progress.
  7. All Engineering submissions are in progress.

 

2024-01-31

Viewz-01
•    Fencing Work Completed- 100%
•    Project Signboard Installation completed.-100%
•    Appointment of shoring Contractor – Completed and Changed from M/s Geo foundation to M/s Atlas Foundation.
•    TIS application approved by RTA. Payment processed - Completed.
•    All other Construction and Design NOC’S are completed.
•    Building permit application will be processed upon drawing approval.
•    Enabling subcontractor started mobilisation.

Viewz-02
•    Shoring Guide-wall works 100% completed.
•    Excavation works of Enabling contractor 100% completed.
•    Building permit obtained under the name of Main Contractor (M/s Prestige)
•    Shoring works 100% completed.
•    Main pile design submitted to DM.
•    Dewatering system submission is in progress.
•    All Engineering submissions are in progress.