PROGRESS ( 30-Nov-2022 )

Excavation
100%
Shoring
100%
Concrete
99.5%
Blockwork
99.8%
Internal Plaster
99.5%
Electrical
57%
Hvac
79.08%
Glass Aluminium
81.3%
Wooden doors
25.63%
Wardrobe
60.87%
Kitchen
61%
Plumbing
81.51%
External Plaster
97%
Internal Paint
61.3%
External Paint
75%
Tiling Marble
72.08%
Mechanical
78.35%
Handrail Fencing
58.76%
False ceiling
64.2%
Lighting
15%
Bath sanitary
5%